Question : FOUR LANING OF N.H-76



(a) whether the work of converting two-lane NH-76 into four-lane under East-West Corridor of National Highways Authority of India is slow;

(b) if so, the reasons therefor and the present status of progress, till date; and

(c) the details of land acquisition, invitation of tenders and placing work-orders for construction of by-passes, bridges/culverts etc. in Kota, Bundi and Baran districts alongwith the details of expenditure likely to be incurred thereon?

Answer given by the minister



THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS(SHRI K. H. MUNIYAPPA)


(a) to (c) Total length of NH-76 under East – West Corridor (excluding the common portion of Udiapur – Chittorgarh with Golden Quadrilateral) is 525 km, which is being converted from two lane to four lane. The land for the above stretch on NH-76 has been acquired. The details and present status including that of construction of bypasses, bridges/culverts, etc. in Kota, Bundi and Baran Districts as well as likely expenditure thereto for the contracts on NH–76 are given at Annexure – I.

EAST WEST CORRIDOR

S. No.	Contract	NH No.	Expenditure likely to	Present Status	Stretch (State)	Length (km.)	be incurred (Rs. crores)
1
Shivpuri Bypass & upto Madhya Pradesh /Rajasthan Border
Km 609 to km 579 & Shivpuri Bypass (Madhya Pradesh)
76
53
360.34
Agreement signed on 17.6.2005
2
Rajasthan /Madhya Pradesh Border to Kota
Km 575 to km 509 (Rajasthan)
76
70.00
311.35
Agreement signed on 20.07.2005
3
Rajasthan /Madhya Pradesh Border to Kota
Km 509 to Km 449.15 (Rajasthan)
76
59.85
378.22
Letter of Acceptance (LOA) issued on 30.06.2005
4
Rajasthan /Madhya Pradesh Border to Kota
Km 449.15 to Km 406.00 (Rajasthan)
76
43.15
297.72
LOA issued on 30.06.2005
5
Kota Bypass Km 406.00 to km 381.00 (Rajasthan)
76
25.00
228.00
Technical Bids are under evaluation
6
Chambal Bridge
(Rajasthan)
76
1.35
200.00
Bid Documents are under finalization
7
Kota to Chittorgarh
km 381.00 to km 316.00 (Rajasthan)
76
65.00
446.40
LOA issued on 30.06.2005
8
Kota to Chittorgarh
km 316.00 to km. 253.00 (Rajasthan)
76
63.00
440.60
LOA issued on 30.06.2005
9
Chittorgarh Bypass
km 253.00 to km 215.00 (Rajasthan)
76
40.00
384.25
L OA issued on 31.05.2005
10
Gogunda to Udaipur
km 73 to km 104.74
(Rajasthan)
76
32.00
266.00
LOA issued on 31.05.2005
11
Bekaria to Gogunda
km 29 to km 73
(Rajasthan)
76
44.00
457.00
Agreement signed on 08.08.2005
12
Pindwara to Bokaria
km 0.00 to km 29.00
(Rajasthan)
76
29.00
220.00
LOA issued on 31.05.2005
Note: The length of stretch of NH-76 in Districts of Kota, Bundi & Baran is as under:
Kota - 60 km.
Bundi - 40 km.
Baran - 141 km

******