Question : CONSTRUCTION OF TERMINAL AT RAIGARH RAILWAY STATION



(a) the date on which approval was given for construction of Terminal at Raigarh Railway Station under Bilaspur Railway Division and for laying of new rail line from Bishrampur to Ambikapur ; and

(b) the allocations made therefor during 1999-2000 and 2000-01 along with progress made in regard to the above projects ?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH)

(a) Approval for construction of Raigarh Terminal under Bilaspur Division was given in 1998-99.

A new Railway line from Bishrampur to Ambikapur was included in 1997-98(Supplementary Budget). Approval of Planning Commission was received in August, 1998.

(b) Allocations made for construction of Raigarh Terminal during 1999-2000 and 2000-01 were Rs. 87.89 Lakhs and Rs. 40.00 Lakhs respectively. Land acquisition for the project is being processed.

Allocations made for construction of Bishrampur-Ambikapur new line during 1999-2000 and 2000-01 were Rs. 5.3 Crores and Rs. 5 Crores respectively. Physical possession of full private land has been obtained in December 1999. Tenders for earth work, bridges and buildings are being processed.