Question : CONSTRUCTION OF TRIVANDRUM NH-47 BY-PASS



(a) whether the construction work of Trivandrum By-pass on NH-47 is going on as per schedule;

(b) if so, the present status thereof;

(c) the details of the allocation made and utilised so far; and

(d) the time by which the work is likely to be completed?

Answer given by the minister


MINISTER OF STATE FOR ROAD TRANSPORT AND HIGHWAYS (INDEPENDENT CHARGE) (MAJOR GENERAL (RETD.) B.C. KHANDURI, AVSM)


(a)&(b) Construction of Trivandrum bypass of about 44.53 Km. length has been taken up in two phases. In Phase-I the work has been completed in about 19.5 Km. out of the total length of 22.63 Km. The progress of work is behind the schedule. For Phase-II, land acquisition is in progress in 3.271 Km. out of the total length of about 21.9 Km.

(c) Allocation for National Highway works are made State-wise and not National Highway wise. The upto date expenditure on this bypass is about Rs.44.81 Crore.

(d) The Phase-I of the bypass is targetted to be completed by December, 2002. In Phase-II of the bypass the work of land acquisition has been taken up in part length. Therefore, it is too early to indicate the date of completion of Phase-II.