THE MINISTER OF STATE FOR COAL (SHRI SYED SHAHNAWAZ HUSSAIN)
(a): Nineteen coal washeries are in operation in the
subsidiary companies of CIL. The capacity and clean coal
production for the last three years are given below:-
Sl. Name of Washery Raw Coal 98-99 99-2000 2000-01 No. throughput capacity Prodn. Prodn. Prodn. (MTY) (MTY) (MTY) (MTY)
1 DUGDA-I, BCCL 1.00 0.44 0.37 2 DUGDA-II, 2.00 0.40 0.47 0.37 BCCL 3 PATHERDIH, 1.6 0.28 0.28 0.24 BCCL 4 LODNA, BCCL 0.48 0.14 0.16 0.11 5 SUDAMDIH, 1.6 0.32 0.36 0.32 BCCL 6 MOONIDIH, 1.6 0.44 0.51 0.43 BCCL 7 BARORA, BCCL 0.42 0.11 0.17 0.10 8 MOHUDA, BCCL 0.63 0.22 0.26 0.25 9 MADHUBAN, 2.5 0.03 0.13 0.14 BCCL 10 KATHARA, CCL 3.0 0.56 0.54 0.61 11 SWANG, CCL 0.75 0.44 0.36 0.33 12 RAJARAPPA, 3.0 1.00 0.80 0.81 CCL 13 KEDLA, CCL 2.6 0.39 0.35 0.34 14 KARGALI, CCL 2.72 0.69 0.69 0.73 15 GIDI, CCL 2.5 0.48 0.64 0.60 16 PIPARWAR, CCL 6.5 4.67 5.40 4.46 17 NANDAN, WCL 1.2 0.35 0.30 0.28 18 BINA, NCL 4.5 0.49 0.74 19 BHOJUDIH, 1.7 0.80 0.84 0.76 BCCL
(b) to (d): Details are furnished as under:-
Sl. Name of Washery Processi Cost Ash % Ash % No. ng of before after cost/T coal/T washing washing of clean after coal(Rs.) washing (Rs.)
1 DUGDA-I, BCCL 432.8 886.13 48.5 35.5 2 DUGDA-II, 901.6 2653.00 33.0 19.94 BCCL 3 PATHERDIH, 1035.3 2808.29 29.1 19.96 BCCL 4 LODNA, BCCL 615.04 2255.6 31.5 20.03 5 SUDAMDIH, 979.3 2671.64 30.3 19.74 BCCL 6 MOONIDIH, 663.6 1700.90 28.2 19.0 BCCL 7 BARORA, BCCL 946.21 2639.9 27.9 18.86 8 MOHUDA, BCCL 564.35 2204.5 22.5 18.5 9 MADHUBAN, 2627.6 4145.64 33.2 20.15 BCCL 10 KATHARA, CCL 562.48 1940.97 31.7 19.2 11 SWANG, CCL 471.17 1653.8 35.5 19.3 12 RAJARAPPA, 344.9 1848.72 34.3 19.7 CCL 13 KEDLA, CCL 915.25 2809.61 31.2 19.5 14 KARGALI, CCL 438.01 1099.54 42.5 33.1 15 GIDI, CCL 371.11 1437.53 43.5 33.0 16 PIPARWAR, CCL 43.92 769.63 39.9 34.3 17 NANDAN, WCL 459.93 1760.00 29.0 18.0 18 BINA, NCL 58.36 749.77 E&F 33.41 Gr. 19 BHOJUDIH, 491.9 2033.72 25.0 19.67 BCCL
(e): No washery has been installed in MCL by CIL.
(f): It has been reported by Coal India Ltd., that they
had finalised to set up two non-coking coal washeries at
Kalinga and Ananta-Bharatpur under Build-Own-Operate
scheme in MCL. But in the absence of any consensus on
the quantum of washing charges, the construction of the
washereis under Build-Own-Operate scheme have not been
taken up.