THE MINISTER OF POWER ( SHRI P.M. SAYEED )
(a) & (b) : The details of the National and Regional level Public Sector
Undertakings (PSUs) engaged in operation and commissioning / construction of hydro
power projects in the country along with their economic profile, rating and installed
capacity of operating projects are given in Annexure-I. The status of each project under
execution by these PSUs with targets set for completion is given in Annexure-II.
(c) : The details of the projects tentatively assigned to them for future
development in India are given in Annexure-III. In addition, allocation of some of the
selected low tariff hydroelectric schemes identified under 50,000 MW Hydroelectric
Initiative, to these PSUs for implementation, is under process in consultation with the
State Governments. Besides, consultations are also being held with the concerned State
Governments for allocation of four projects in the Cauvery Basin to National
Hydroelectric Power Corporation Limited for execution.
(d) : No such proposal is under consideration of the Government.
(e) : Question does not arise.
ANNEXURE-I
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) & (b) OF
UNSTARRED QUESTION NO. 7279 TO BE ANSWERED IN THE LOK SABHA
ON 13.05.2005.
Statement indicating the names of National and Regional
level Power Sector Undertakings (PSUs) engaged in operation
and commissioning of hydro power projects in the country
with economic profile, rating etc.
Sl. Name of the Paid up Audited Category# Install Credit
No. PSUs Capital profit ed Rating## (as on after Capacity 31.03.2004) tax (Hydro) (Rs. in during (MW) Crs.) 2003-04 (Rs. in Crs.)
1. National 8,269.03 621.38 A 2,475 AAA Hydroelectric Power Corporation Ltd. (NHPC)
2. Narmada Hydro- 1,932.42 12.37 @@ 1,000 Not electric rated Development Corporation Ltd. (NHDC)
3. North Eastern 1,953.26 197.58 B 755 Not Electric Power rated Corporation Ltd. (NEEPCO)
4. Satluj Jal 3,081.00 218.00 B 1,500 Not Vidyut Nigam rated Limited (SJVNL)
5. Tehri Hydro 2,968.43 @ B Under Not Development Constru- rated Corporation ction Ltd. (THDC)
6. National 7,812.55 5,260.80 Nav Under AAA Thermal Power Ratna Constru- Corporation ction (NTPC)
@ No project is currently under operation.
@@ NHDC is still to be categorized.
# Categorization as per schedule of Department of Public Enterprises.
## The credit rating for domestic capital market borrowing has been indicated.
ANNEXURE-II
ANNEXURE-II REFERRED TO IN REPLY TO PARTS (a) & (b) OF UNSTARRED QUESTION NO. 7279
TO BE ANSWERED IN THE LOK SABHA ON 13.05.2005.
Statement indicating the status of the projects under construction with installed capacity,
location and targets set for completion Sl. Name of the Name of the Installed Targeted No. PSUs / Name of State/ District Capacity year of the Project (MW) commissioning National Hydroelectric Power Corporation Ltd. 1. Dhauliganga Uttaranchal/Pitho 280 2005-06 ragarh 2. Dulhasti J&K / Doda 390 2005-06 3. Teesta Stage-V Sikkim / East 510 2006-07 Sikkim 4. Sewa-II J&K / Kathua 120 2007-08 5. Teesta Low Dam- West Bengal / 132 2007-08 III Darjeeling 6. Parbati Stage- H.P./ Kullu 800 2009-10 II 7. Subansiri Ar. Pr. / L. 2,000 2010-11 Lower Subansiri / Dhemaji Total 4232 Narmada Hydroelectric Power Corporation Ltd. 8. Omkareshwar M.P./ Khandwa 520 2006-08 Tehri Hydro Development Corporation Ltd. 9. Tehri Stage-I Uttaranchal / 1000 2005-06 Tehri Garhwal 10. Koteshwar Uttaranchal / 400 2006-07 Tehri Garhwal Total 1400 North Eastern Electric Power Corporation Ltd. 11. Tuirial Mizoram / Aizwal 60 # 12. Kameng Ar. Pr. / Kameng 600 2009-10 Total 660 National Thermal Power Corporation Ltd. 13. Kol Dam H.P. / Bilaspur 800 2008-10
# = Work on the projects is held up.
ANNEXURE-III
ANNEXURE REFERRED TO IN REPLY TO PART (c) OF UNSTARRED QUESTION NO. 7279 TO BE ANSWERED
IN THE LOK SABHA ON 13.05.2005.
The details of the projects tentatively assigned to PSUs for future development in India# Sl. Name of the PSUs / Name Installed No. of the Project Capacity (MW) National Hydroelectric Power Corporation Ltd. 1. Chamera-III 231 2. Parbati Stage-III 520 3. Kishanganga 330 4. Uri-II 240 5 Nimoo Bazgo 45 6. Chutak 44 7. Teesta Low Dam-IV 160 8. Siang (Upper) / Siang To be decided (Intermediate) 9. Devade 6 10. Bav HEP Stage-II 20 11. Siang Lower 1600 12. Kotli Bhel Stage-IB 280 13. Kotli Bhel Stage-1A 240 14. Kotli Bhel St-II 440 15. Pakal Dul 1000 16. Bursar 1020 17. Subansiri Middle 1600 18. Subansiri Upper 2000 19. Siyom(Siang Middle) 1000 20. Dibang 3000 Tehri Hydro Development Corporation Ltd. 21. Tehri-PSS 1000 22. Vishnugad Pipalkoti 440 National Thermal Power Corporation Ltd. 23. Loharinagpala 600 24. Tapovan Vishnugad 520 25. Lata Tapovan 125 North Eastern Electric Power Corporation Ltd. 26. Tuivai 210 27. Tipaimukh 1500 28. Hirit 50 29. Papumpam 60 30. Bhareli Lift Dam 330 31. Ranganadi Stage-II 130 32. Lower Kopili 150 33. Dikrong 110 Satluj Jal Vidyut Nigam Limited 34. Rampur 434
# The above list is tentative and is subject to the PSU obtaining various clearances from Central/State agencies.