THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES (SMT. BIJOYA CHAKRAVARTY)
(a) & (b) The amount of external assistance received by
State Governments during the last two years is given in
Annexure. There are a number of ongoing projects with
external assistance as shown in the Annexure.
(c) & (d) There is one ongoing water resource project
receiving foreign funding in Karnataka. The agreement for
the project âKarnataka Community Based Tank Management
Project âhas been signed on 06.06.2002 for World Bank
assistance of SDR 80 million. The project is scheduled for
completion by 31.1.2009.
ANNEXURE
STATEMENT REFERRED TO IN PARTS (a) & (b) OF THE LOK SABHA
UNSTARRED QUESTION NO.2171 FOR ANSWER ON 02.12.2002
REGARDING FOREIGN ASSISTANCE FOR WATER RESOURCE PROJECTS.
Details of ongoing externally aided projects during the years 2000-2001 and 2001-2002
A) WORLD BANK
S. Name of Date of Assistance Assistance
No Projects Agreement/C amount received Status ompletion in Million (Disbursement) US $/SDR Million US $ During 2000- 2001- 2001 2002
1 Andhra 03.06.1997 US$ 325 27.10 23.14 Ongoing
Pradesh 31.01.2003 Credit. Recomme
Irrigation US$ 150.00 nded
Project-III LoanLUS$ for
Cr.2952-IN 175.00 extensi
Ln-4166-IN on for two years beyond 31.1.2003
2 A.P.Economic 30.01.1999 US$ 142 12.63 10.62 Ongoing
c 31.03.2004 IRDB
Restructuri Loan
ng Project
(Irrigation
component)
Ln-4360-IN
3 Haryana 24.6.1994 US$ 258 41.50 52.93 Completed
Water 31.12.2001
Resources
Consolation
Project
CR-2592-IN
4 Karnataka 06.06.2002 SDR 80 0.00 0.00 Ongoing
Community 31.1.2009
Based Tank
Management
Project
5 Orissa 05.01.1996 SDR 290.90 29.26 16.63 Ongoing
Water 31.3.2004
Resource
Consolidati
on Project
Cr.2801-IN
Rajasthan 15.3.2002 SDR 110 0.00 5.00 Ongoing
6 Water 31.3.2008 Credit
Sector Effecti
Restructuri ve from
ng Project 27.3.20
Cr.3603-IN 02
7 UP Water 08.3.2002 SDR 117 0.00 5.00 Ongoing
Sector
Restructuring 31.10.2007 Credit
Project Effect
Cr.3603-IN ive from 22.3.2 002
8 Tamil Nadu 22.09.1995 US $ 32.34 20.36 SDR 20
Water Resource 282.90 million
Consolidation 31.03.2003
Project cancel
Cr.2745-IN led.
9 Hydrology 22.9.1995 SDR 75.1 15.79 9.55 Ongoing
Project
Multi-States 31.03.2003
Sub Total 158.62 143.23
B. EUROPEAN ECONOMIC COMMUNITY
S.No Name of Date of Amount of Assistance Status Projects Agreemen Assistance received t/Comple- Million (Disburseme tion EURO nt) (Million EURO During 2000- 2001- 2001 2002
1 Kerala Minor 21.5.1992 ECU 11.80 0.62 0.00 Completed
Irrigation
Project 31.12.2000
(Kerala)
2 Sidhmukh & 7.6.1993 ECU 45.00 0.00 5.715 Completed
Nohar 31.12.2001
Irrigation
Project
(Rajasthan)
3 Orissa Minor 3.7.1995 ECU 10.70 0.64 0.00 Ongoing
Irrigation 31.12.2004
Project
(Orissa)
4 Modernisation 21.2.1997 ECU 6.65 0.00 0.817 Ongoing
of Tank
Irrigation 21.2.2003
System
(Pondicherry)
5 Saline Land 11.7.1995 ECU 15.50 0.00 1.229 Ongoing
Reclamation
Project Phase-II 31.12.2005
(Maharashtra)
Sub Total 1.26 7.761
C. BILATERAL PROJECTS
S.No Name of Projects Fundi Date Assista Assistance ng of nce received Agency Agreem amount (Disburseme Status ent/Co in nt) mpleti Million (Million on DC DC) During 2000- 2001- 2001 2002
1 Rajasthan CIDA, 13.3.1990 CAD 0.062 0.00 Completed
Agricultural Canada 14.99
Drainage Project 31.12.2000
(Rajasthan)
Sub-Total 0.062 0.00
2. Hydroplus Fran 17.5.1999 FF 3.53 2.28 Completed
Fusegate System ce 34.74
(Gujarat) 31.12.2001
3. Ground Water Fran 23.11.1998 FF 3.09 0.62 Completed
Exploration ce 4.62
Project(Manipur) 31.12.2001
Subtotal 6.62 2.90
4. Modernisation on JBIC 25.01.1996 Yen 1483.64 2225.07
KC canal project Japa 16049.00 Ongoing
(Andhra Pradesh) n 26.3.2003
5. Rajghat Canal JBIC 25.02.1997 Yen 1377.51 1921.77 Ongoing
Project (Madhya , 13222.00
Pradesh) Japan 31.03.2004
6. Rengali JBIC 12.12.1997 Yen 900.10 839.28 Ongoing
Irrigation , 7760.00
Project(Orissa) Japan 05.2.2003
Sub Total 3761.25 4986.12
7. Maharashtra KfW, 21.12.1998 DM 0.37 1.96 Ongoing
Minor Germany 45.00
Irrigation 31.12.2006
project
(Maharashtra)
8 Lift KfW, 19.02.1993 DM 2.68 2.02 Ongoing
Irrigation Germany 55.00
Project(Oris 30.6.2003
sa) Sub Total 3.05 3.98
9 AP-WELL Netherla 14.11.1994 NLG 0.45 0.93 Ongoing
Irrigation nds 26.847
Project 31.03.2
(Andhra 003
Pradesh)
10. Community Netherla 17.12.1993 NLG 0.046 0.00 Completed
Irrigation nds 2.328
Project 31.3.2002
(Kerala)
11 Bundelkhand Netherla 12.06.1996 NLG 0.00 0.00 Completed
Water nds 2.79
Resources 31.05.2001
Management
Project
(Uttar radesh)
Sub Total 0.596 0.93
STATEMENT REFERRED TO IN REPLY TO PARTS (b) & (c)
OF LOK SABHA UNSTARRED QUESTION NO.2108 FOR ANSWER
ON 02.12.2002 REGARDING IRRIGATION PROJECTS UNDER AIBP
Sl. Name of CLA Released (Rs. in crore)
No. Project 1999- 2000-01 2001-02 Total 2000
1. UKP Stage âI 100.000 100.000 200.0000 400.000 (IV)
2. Malprabha 13.500 - 10.000 23.500 (III)
3. Hirehalla 8.000 8.000 10.000 26.000 (VI)
4. Ghataprabha 20.000 45.000 5.000 70.000 (V)
5. Karanja (V) 15.640 18.000 10.000 43.640
6. UKP State-II - - 250.000 250.000 (IX)
7 Gandorinala - - 7.5000 7.5000 (VIII)
Total : 157.140 171.000 492.500 820.640