Question : IMPLEMENTATION OF PROJECTS BY CPWD



(a) whether the Central Public Works Department is having more than 3000 projects without proportionate strength of engineers to deal with them;

(b) if so, the reasons therefor;

(c) the number of cases assigned to CPWD engineers;

(d) the number of projects that are held up;

(e) whether lack of coordination is one of the factors affecting the projects as well as their maintenance; and

(f) if so, the corrective measures taken by the Government in this regard?

Answer given by the minister



MINISTER OF PARLIAMENTARY AFFAIRS AND URBAN DEVELOPMENT( SHRI GHULAM NABI AZAD )

(a)&(b): CPWD has more than 3000 original works. The sanctioned strength of engineers is sufficient for handling these works. However, there are a number of vacancies in different grades which has put additional burden on the existing manpower.

(c): About 1225 major works, costing more than Rs.1 crore each and 1350 works costing above Rs.10 lakh each have been assigned to CPWD engineers. Apart from this, a number of projects having smaller value are also being handled by CPWD.

(d): No project is held up for lack of manpower. However, some projects get delayed due to a variety of reasons including intervention by Courts, adverse law and order situations etc.

(e): Lack of adequate coordination among different disciplines of CPWD and with the client Departments is one of the factors which affects execution of the projects.

(f): Government monitors these projects by regular reviews at various levels so as to ensure timely completions.