Question : INCOMPLETE CONSTRUCTION WORK



(a) whether the construction work on several stretches on NH-13, NH-17 and NH-48 has not been completed within the stipulated time;

(b) if so, the details thereof alongwith the reasons therefor, NH-wise and State-wise where such NH passes through;

(c) the details of the steps taken by the Government to expedite the completion of such construction work and the action taken against the defaulting contractors/officers responsible for the construction of the delayed stretches; and

(d) the time by which the construction is targeted to be completed?

Answer given by the minister


MINISTER OF THE STATE IN THE MINISTRY OF ROAD TRANSPORT AND HIGHWAYS (SHRI R.P.N. SINGH)

(a) Yes, Sir.

(b) Details are annexed.

(c) Steps have been taken to expedite land acquisition by urging State Government to take proper steps. Contracts of defaulting contractors have been terminated and contract reawarded in one case.

(d) Completion is targeted by August, 2011, except for the terminated contracts.