THE MINISTER OF HEALTH AND FAMILY WELFARE (SHRI GHULAM NABI AZAD)
Â
Â
(a): There has been some delay in setting up of the six new AIIMS-like institutions under the
PMSSY scheme. The initial delays were due to failure of bids for selection of single Project
Consultant and selection of Prototype Architectural Design for all the six AIIMS-like
institutions. The whole process had to be initiated de novo in Dec.2006 and each site has now
been taken up separately. The process of finalizing/approving the Detailed Project Reports
(DPRs) has also taken some time as it required due vetting by medical and other technical
experts.
Â
(b): As the recruitment of manpower is key to the efficient running of these institutions, the
residential complexes to house the faculty and staff is being constructed on priority
construction and will be ready by 2009-10 at all six sites. The Hospital/Medical College
complexes are expected to be ready by 2011.
(c): There is no separate institute-wise allocation. The funds allocated for the PMSSY scheme
and year-wise expenditure position is as follows:-
(Rs. in crores)
Year BE RE Expenditure
2006-07 75.00 10.00 6.37
2007-08 150.00 90.00 88.70
2008-09 490.00 568.00 498.13
2009-10 647.92 - 29.11#
Â
# as on 30th June 2009
Â
(d)&(e): All necessary steps are being taken to expedite execution of the project. There is
regular monitoring of the project by the Project Management Committee (PMC) headed by Secretary
(Health), Govt. of India.
Dedicated Project Cell(s) comprising of Medical experts, Engineers and administrative staff
have been set up at each site.
Â
Institutions are proposed to be established and operationalized by 2011-12.