Question : PMGSY in Chhattisgarh

(a) the number of additional projects under consideration of the Government for approval under Pradhan Mantri Gram Sadak Yojana (PMGSY) in Chhattisgarh during the current year;

(b) the details of the ongoing projects under PMGSY in Raj nandgaon and Kabirdham districts of Chhattisgarh during the last two years; and

(c) the details of the total funds allocated and spent in the said districts during the said period?

Answer given by the minister

MINISTER OF RURAL DEVELOPMENT
(SHRI NARENDRA SINGH TOMAR)

(a) The State of Chhattisgarh has been allocated a road length of 5,612.50 Km under phase-III of Pradhan Mantri Gram Sadak Yojana (PMGSY). The first batch of proposals of 355 roads of 3,729.17 km and 10 Bridges of 580.58 m have already been sanctioned to the State. The State has now submitted batch-II of proposals of 207 roads of 2,214.14 Km and 8 Bridges of 726.10 m under PMGSY-III . The balance eligibility of the State vis-à-vis allocated length is only 1,883.33 Km.

(b) As reported by the State Government of Chhattisgarh, the details of ongoing projects under PMGSY in Rajnandgaon and Kabirdham districts of Chhattisgarh during the last two years are given at Annexure.

(c) The details of funds allocated and spent in Rajnandgaon and Kabirdham districts during the last two years, as reported by the State Government are given below:-

(Rs. in crores)
S.N. Name of District Fund allocated during Expenditure during
last two years last two years

1 2 3 4

1 Rajnandgaon 229.84 229.84

2 Kabirdham 63.98 63.98


*******


ANNEXURE