THE MINISTER OF POWER (SHRI SUSHILKUMAR SHINDE)
(a) & (b) : Siyom (Siang Middle) Hydroelectric project (HEP) (1000 MW) and Siang
Lower HEP were transferred by Government of Arunachal Pradesh on 22.3.2000 for
execution by National Hydroelectric Power Corporation Limited (NHPC) in the Central
Sector. However, the Government of Arunachal Pradesh has since entered into a
Memorandum of Agreement on 22.2.2006 for execution of these projects through private
developers. In addition to these two projects, three other projects, viz. Tato-II HEP (700
MW), Naying HEP (1000 MW) and Hirong HEP (500 MW) for which the work of
preparation of Detailed Project Reports (DPRs) was entrusted to NHPC under the 50,000
MW Hydroelectric Initiative, have also been entrusted to private developers by the State
Government. No reasons have been given by Government of Arunachal Pradesh for
replacing NHPC by private developers for implementation of these projects.
(c) & (d) : A total number of 9 projects are held up in Arunachal Pradesh and
Manipur due to non-receipt of clearance from the Ministry of Environment & Forests.
Details of these projects are given in Annexure.
(e) : The reassessment studies of hydroelectric potential of the country,
completed by Central Electricity Authority in 1987, have placed the hydro power
potential at 84,044 MW at 60% load factor. Of this, the potential of Arunachal Pradesh is
26,756 MW.