THE MINISTER OF STATE IN THE MINISTRY OF MINES (DR. T. SUBBARAMI REDDY)
(a) to (d) : Yes, Sir. After obtaining Government approval on 26.10.2004, National Aluminium
Company Limited(NALCO) has started implementation of second phase expansion project of its
integrated aluminium complex at a revised estimated cost of Rs. 5003 crores (March, 2007
price levels) which is to be completed by December, 2008. The present capacity of the
various project segments and the projected capacity after 2nd phase expansion is as under:-
Project Segment Unit Present capacity Projected capacity after 2nd phase expansion
Bauxite Mines Lakh MT# 48 63
Alumina Refinery Lakh MT 15.75 21
Aluminium Smelter Lakh MT 3.45 4.6
Captive Power Plant Mega Watt 960 1200
#MT- Metric Tonne
The overall physical progress of the various project segments as on October, 2007 is as
follows:-
Project Segmen Physical progress
Mines & Alumina 48.1 %
Smelter 46.5%
Captive Power Plant 66.7%