THE MINISTER OF STATE IN THE MINISTRY OF POWER ( SHRI K.C. VENUGOPAL )
(a) & (b) : Coal stock position of state run power
companies/utilities including those run by NTPC Limited at the
end of each month from September, 2011 to February, 2012 and
as on 26th March, 2012 is given at Annex-I.
(c) : Ministry of Coal had advised Coal India Limited that
the quantity of coal earmarked for sale under e-auction during
October, 2011 by the coal companies may be offered to the
Power Utilities on `as is where is basis`, giving them 15 days to
confirm the quantity to be lifted, by making their own
arrangements. According to NTPC, the coal offered by Coal India
Limited was Run-of-Mine (ROM), uncrushed and lying on mine-
mouth and Coal India Limited did not agree to crush and
transport the coal to railway sidings.
(d)& (e) : Due to inadequate availability of domestic coal, domestic
coal companies are not in a position to supply full quantity of coal as
per Linkage/ LOA to power plants. As a result of this, Power Utilities
are required to use imported coal to bridge the short fall. Use of
imported coal and rise in cost of imported coal has impacted
electricity generation as well as its cost. Generation loss of 8.7
Billion Unit has been reported by the Power Utilities during April,
2011 to February, 2012 due to inadequate availability of coal.
Increase in cost of generation due to blending of imported coal with
domestic coal depends on the quality / grade of imported and
domestic coal, origin of country transportation from port to power
station, etc.The Ultra Mega Power Plants based on imported coal
have also been affected due to increase in cost of imported coal.
Coastal Gujarat Power Limited (CGPL), a TATA Power
Company and the developer of Mundra Ultra Mega Power Project
(UMPP), approached Ministry of Power for its intervention to address
the issues of increase in Indonesian coal price from where the
company is sourcing its coal for Mundra UMPP.
A team of officers of Central Electricity Authority,
Ministry of Power and Andhra Pradesh Power Generation Company
(APGENCO) visited the site of Krishnapatnam UMPP and has
observed that the work has been stopped by the developer inter-alia
due to the increase in the prices of Indonesian coal. The State
Government has also raised the issue and requested for this
Ministry`s intervention.
Power Purchase Agreement (PPA) being a legally binding
document exclusively between the procurer and the developer this
Ministry has advised the lead procurers i.e. Government of Andhra
Pradesh for Krishnapatnam UMPP and Government of Gujarat for
Mundra UMPP that any issues arising therein is to be settled within
the provisions of PPA by the contracting parties for which lead
procurer may taken necessary action.
Following steps have been/are being taken by the Government to
mitigate shortage of coal for the thermal power plants in the country :
# Ministry of Coal/Coal India Ltd. are being insisted upon to enhance production of domestic coal in the country.
# Power Utilities have been advised to import coal to the extent technically feasible to bridge the gap between requirement of coal and its availability from domestic sources.
# The coal supply position to thermal power stations is regularly reviewed in Ministry of Coal, Ministry of Power and Cabinet Secretariat with participation from the concerned Ministries, Central Electricity Authority, Coal India Limited and NTPC.
# Reduction in e-auction by CIL from 10% to 7% of its production progressively till the end of 12th Plan, if required, to meet its commitment to power sector.
(f) : The estimated requirement & availability of coal as well as
shortage for Power Utilities during the next three years as per Report of the
Working Group on Power for 12th Plan submitted by Ministry of Power to
Planning Commission is given at Annex-II.