Question : Flyovers on Delhi-Jaipur Expressway

(a) the number of flyovers sanctioned by the Government on Delhi-Jaipur expressway and the details of the flyovers completed and the number of flyovers at to be completed;

(b) whether any time limit has been fixed by the Government to complete the works of incomplete flyovers;

(c) if so, the details thereof;

(d) whether the budget to make Delhi-Jaipur highway free from jams by construction of more flyovers has been increased; and

(e) if so, the details thereof?


Answer given by the minister

THE MINISTER OF STATE IN THE
MINISTRY OF ROAD TRANSPORT AND HIGHWAYS

(SHRI PON. RADHAKRISHNAN)

(a) to (e) Feasibility study of the Delhi-Jaipur Expressway is in progress. In view of high cost of land acquisition, innovative financial options are being explored. However, as far as the existing Delhi-Jaipur Highway (NH-8) is concerned, following is the status:

• Total 93 structures (Flyovers/VUP/PUP) have been proposed on six laning of Delhi- Jaipur Project which is on BOT mode.
• Out of the 93 structures, 9 structures have been deleted & 17 structures have been delinked due to non availability of land. Construction of the 17 delinked structures envisaged in the project for smooth flow of traffic depends upon availability of encumbrance free land.
• Out of the balance 67 structures, 61 structures have been completed and 5 structures are targeted to be completed by June 2016 and one flyover (at Hero Honda Chowk) is targeted to be completed by May 2017. A budgetary provision of Rs. 53.90 crore has been kept during the Financial year 2015-16 for construction of flyover at Hero Honda Chowk on EPC mode. After construction of flyover at Hero Honda Chowk, congestion on the project highway is likely to be decreased.
• List of 61 completed structures is enclosed as Annexure