Question : Upgradation of SHs into NHs

(a) the details of State Highways (SHs) that have been converted into National Highways (NHs) in the country during the last five years and the current year in the country, State-wise including Karnataka and Telangana;
(b) the present status of ongoing upgradation of SHs into NHs in the said two States; and
(c) the target set for completion of the up-gradation of SHs into NHs along with the details of funds allocated and spent on these projects in the said two States?

Answer given by the minister

THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS

(SHRI NITIN JAIRAM GADKARI)
(a) State/Union Territory (UT)-wise details of State roads including State Highways (SHs) notified as National Highways (NHs) in last 5 years and current year is annexed.
(b) and (c) The Ministry is primarily responsible for development and maintenance of NHs. Development and maintenance of SHs is the responsibility of the concerned State Government / Union Territories (UTs). Present status of ongoing NHs works in the state of Telangana and Karnataka is as under.

State No. of ongoing development works Length of ongoing works (km) Sanctioned amount of ongoing works (Rs. Crore) Length completed (km) Expenditure incurred (Rs. In crore) Target for completion of works
Telangana 42 1,368 18,890 543 4,008 2022 - 2024
Karnataka 73 2,138 37,112 1,272 13,621 2022 –2024