MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI BANDARU DATTATRAYA )
(a) to (d) : Ministry of Railways have not received any proposal for a
new Railway project from the Government of Jharkhand during the
last one year. Railways have, however, entered into a Memorandum-
of-Understanding with the Government of Jharkhand for execution of
certain specified projects on cost sharing basis.
Details of all ongoing projects in Jharkhand, including
expenditure on each project by the end of March, 2002 and their
progress are given in Appendix.
Details of ongoing surveys in the state of Jharkhand are as under:-
New Lines
1 Gaya-Chatra
2 Hazaribagh-Garwa Road
3 Tori-Shivpur
4 Jhajha-Giridih via Sonuchakai
5 Tori-Chatra
6 Lohardaga-Korba
7 Barwadih-Chirimiri : Restoration of line
Doubling
1 Bhagalpur-Barharwa
2 Chakradharpur-Bondamunda
3 Patratu-Chandil via Barkakana
The surveys are in various stages of progress.
(e) : Improvement and expansion of Rail Network is an integrated
activity where system requirements are taken into consideration.
Data relating to this activity is not maintained state-wise.
Railway Zone-wise data is available in the Budget papers placed in
the Parliament.
APPENDIX
APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (d) OF LOK SABHA UNSTARRED QUESTION NO. 2636 FOR 01.08.2002
On-going Railway Projects in Jharkhand
S. Name of Rly. Latest Outlay Status
No. Project Anticip expected ated by Cost the end of 2001-02
(Amount in Crores of Rupees)
New Lines
1 Deogarh-Dumka ER 172.98 7.13 Final location survey has been completed. Proposal for land acquisition have been submitted. The work will be takenup once the land becomes available.
2 Deogarh- ER 312.00 17.04 Final location survey for
Sultanganj Deogarh-Banka and Banka-
including MM Barahat completed. Part
Ext from Banka- estimate from Deogarh to
Barahat and Katuria (31 km) and Banka-
Banka-Bhitiah Barahat has been
Road sanctioned. Land acquisition papers for this section have been submitted to State Govt. Work has been taken up.
3 Giridih- ER 145.00 7.26 Final location survey has
Koderma been completed. Part estimate (Koderma-Maheshpur 20.5 km.) has been sanctioned. Earthwork & bridges on Koderma-Koderma Town (10 km) has been taken up.
4 Koderma-Ranchi ER 859.79 55.01 Final location survey has been completed. Land papers have been filed with the State Govt. and part land taken over. Earthwork and bridge works have been taken up.
5 Koderma- ER 261.05 0.01 Final location survey is in
Tilaiya progress. Land acquisition has been processed. Work would be taken up once land is handed over by State Government.
6 Rampurhat- ER 170.47 14.46 Final location survey has
Mandarhill via been completed. Land
Dumka acquisition have been processed. The work would be started once the land is made available by the State Government.
Gauge Conversion
7 Ranchi- SER 185.31 22.89 The work for widening of
Lohardaga with formation completed for a
extension to length of 37 km out of 69
Tori km between Ranchi-Lohardaga. On Tori- Lohardaga (44 km) new line portion, fiinal location survey has almost been completed and report is under finalisation.
Doubling
8 Sahibganj-New ER 67.07 67.06 Completed and commissioned.
Farakka-Malda
9 Goelkera- SER 186.92 1.45 Work has lower operational
Manoharpur : priority.
3rd line
Railway Electrification
10 Sitarampur- ER 363.36 358.58 The work has been
Danapur- completed.
Mugalsarai
including
Rampur Dumra-
Garhara-
Barauni
11 Bokarao Steel SER 269.81 265.24 Entire section energised
City-Muri- till March, 2002. Residual
Hatia- works are in hand. The
Bondamunda- project has been delayed
Bimlagarh- due to bad law and order
Kiriburu/Barsu problem and failure of OHE
an incl. contractor and delay in
Purulia- release of 132 KV supply
Kotshila by DVC/BSEB.
12 Chandil-Muri- SER 47.67 42.16 Work has been completed.
Barkakana Residual jobs in hand.