THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES (SHRI JAI PRAKASH NARAYAN YADAV)
(a) & (b) Yes sir, Drought affected areas of the Gujarat and Rajasthan are to get
irrigation facilities from Sardar Sarovar Project.
(c) Implementation of the project has been delayed primarily due to suspension of the work
from 1995 to 2000 during the pendency of Writ Petition (Civil) No.319/1994 in the Hon`ble
Supreme Court filed by Narmada Bachao Andolan and due to slow progress of Resettlement &
Rehabilitation of the project affected persons.
(d) The initial estimated cost of this project was Rs.6406.04 crore at 1986-87 price level
as per investment clearance granted by the Planning Commission in October 1988. Recently,
the Government of Gujarat has submitted the revised estimate of the Sardar Sarovar (Narmada)
Project at 2005-06 price level costing Rs.35045.75 crore for approval.
(e) Irrigation is a Sate subject and planning, funding execution of project as well as
priority of execution of the project is within the purview of the concerned State Government.
The project is being implemented by the State Governments of Gujarat, Rajasthan, Maharashtra
and Madhya Pradesh.