MINISTER OF URBAN DEVELOPMENT & POVERTY ALLEVIATION ( SHRI JAGMOHAN )
(a): Yes, Sir.
(b)to(e): The DDA allotted work relating to construction of 520
MIG Flats in Sector-18, Rohini, Delhi. No specific time for
approval of drawings was given. One week time had been given to
the contractor to submit the drawings. As drawings had to be
got approved from various agencies like DUAC, etc., the same
were got approved after eight months.
Of the 102 blocks on which work was to start, 9 blocks
could not be taken up because of the high tension and low
tension underground cables. The work on 93 blocks was taken up
unhindered.
The first construction agency failed to complete the work
and the work was rescinded. The work was, thereafter, awarded
to the second construction agency. Therefore, the price
escalated. The DDA encashed the bank guarantee of the
contractor amounting to Rs.81.70 lakhs on rescinding the work on 2.11.1994 against which the contractor went to the High Court.
The work has since been completed on 18.9.1999 and possession of
more than 50% flats has been handed over.
The excess cost of Rs.7.29 crores incurred is to be
reclaimed by arbitration as per the terms and conditions of the
agreement. The work has been audited by the DACR Party and in
case of observation of negligence, action accordingly can be
taken.