Question : HARANG DRAINAGE SCHEME



(a) the present status of Harang Drainage Scheme; and

(b) the funds sanctioned/released to the State Government for implementation of the scheme?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF WATER RESOURCES (SMT. BIJOYA CHAKRAVARTY)

(a) The present status of Harang Drainage Development Scheme is as below:-

Land Acquisition	92%
Construction of Embankment	60%
Construction of sluices 
(i) Kinnorkhal 41%
(ii) Kakrakhal 35.75%


(b) The Harang Drainage Development Scheme is a Central Sector Scheme bring implemented by Brahmaputra Board with the revised estimated cost of Rs. 30.49 crore. So far an amount of Rs. 14.42 crore has been released for the above scheme.