Question : PROJECTS UNDER KONKAN RAILWAY



(a) the details of ongoing/pending railway projects under Konkan Railway including Kolhapur-Vaibhavwadi section, project-wise;

(b) the details of funds allocated/spent thereon;

(c) the other steps taken/being taken by the Railways to widen the railway network under Konkan Railway; and

(d) the time frame set for the completion of the pending projects?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI K. H. MUNIYAPPA )

(a): There is no ongoing/pending railway project under Konkan Railway. As far as Kolhapur-Vaibhavwadi section is concerned, on the request of Maharashtra Maritime Board, only preliminary feasibility survey for the proposed Kolhapur-Vaibhavwadi rail connectivity was undertaken by Konkan Railway Corporation Limited and the report was submitted to them in April, 2010. Thereafter, no communication has been received from Maharashtra Maritime Board in this regard.

(b) to (d): Do not arise.