Question : FOUR LANING OF NH BETWEEN MURAINA AND GWALIOR



(a) whether the extension work of the proposed four-laning of the National Highway between Muraina and Gwalior has not been carried out so far;

(b) if so, the details thereof and the reasons therefor;

(c) whether a by-pass has been sanctioned on the said National Highway in Gwalior;

(d) if so, the details thereof and the reasons for delay in the construction of the by-pass;

(e) whether the work is likely to be extended; and

(f) the time by which both these projects are likely to be completed?

Answer given by the minister


MINISTER OF THE STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K.H. MUNIYAPPA)

(a) Yes, Sir.

(b) Muraina-Gwalior section of NH-3 is already four laned. Extension work of six laning of Muraina-Gwalior section has been identified under NHDP Phase-V as a part of Agra-Gwalior section of NH-3. The preparation of detailed project report for six laning is yet to be taken up. For four laning of Gwalior-Dewas section of NH-3, on BOT (Toll) basis and invitation of bids, a Memorandum of Understanding (MOU) with State Government is under consideration.

(c) Yes, Sir.

(d) The work of construction of Gwalior bypass has commenced in April, 2007 on BOT (Annuity) basis. There is no delay at present in the construction schedule..

(e) No, Sir.

(f) The construction of Gwalior Bypass is likely to be completed by October, 2009. It is premature to indicate time frame for completion of six laning of Muraina-Gwalior section and four laning of Gwalior-Dewas section of NH-3.