Question : Dedicated Third Track

(a) whether the Government proposes to implement a dedicated third track in the 107 kms Ernakulam-Shornur corridor in the State of Kerala;

(b) if so, the details thereof and the steps taken by the Government in this regard;


(c) the details of the total cost of implementation and land acquisition in this regard;

(d) whether the Government has any plans to extend the same in future; and

(e) if so, the details thereof?

Answer given by the minister

MINISTER OF RAILWAYS, COMMUNICATIONS AND
ELECTRONICS & INFORMATION TECHNOLOGY

(SHRI ASHWINI VAISHNAW)

(a) to (c): The project of Shoranur-Ernakulam 3rd line (107 Km) has been included in Budget 2018-19 subject to requisite Government approvals. Preparation of Detailed Project Report (DPR) has been taken up which includes land requirement and cost.

(d) and (e): At present, there is no proposal under consideration for extending this proposed 3rd line.

*****