Question : ON-GOING PROJECTS IN RAJASTHAN



(a) the details of the on-going and proposed Railway projects in Rajasthan alongwith the cost involved therein;

(a) the progress made and the amount spent on each of the project so far; and

(b) the time by which these projects are likely to be completed ?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI DIGVIJAY SINGH )

(a) to (c): Details of ongoing Railway projects in Rajasthan along with their cost, expenditure incurred and the progress made are at Appendix-I. Target dates of completion, wherever fixed, have also been indicated in the status of the projects.

Details of surveys being carried out for projects in Rajasthan is at Appendix II.

APPENDIX - I

APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF LOK SABHA UNSTARRED QUESTION NO. 294 FOR 22.02.2001

S. Name of Rly. Cost Expendit Status
No. Project ure upto March, 2000 (Rs. in Crores) On-going Railway Projects in Rajasthan New Lines
1 Dausa- WR 217.93 0.21 Final location survey has been Gangapur completed. Land acquisition papers for first block section covering 34 hectares for first section Dausa- Bamaniya and second block section between Baniyana-Nangal Rajawat submitted to State Govt. Work will be taken up once the land becomes available.
2 Ajmer- WR 67.00 0.00 New work included in the Budget Pushker 2000-01. Final location survey is being taken up. Land acquisition plans and papers are under preparation.
3 Ramganjmandi- WR 425.00 0.00 New work included in the Budget Bhopal 2000-01.Estimate for Final Location Survey has been sanctioned. Final location survey is being taken up. Gauge Conversion
4 Bhildi- NR 185.00 4.35 Works is being progressed as per Samdri availability of resources.
5 Phulera- NR 45.66 0.85 The work from Phulera-Jodhpur has Jodhpur- been completed and commissioned. Pipar Road - The rest of section from Pipar Road Bilara to Bilara has been sanctioned as a Material Modification. Due to low operational priority and very light traffic on Pipar Road-Bilara section, work is temporarily pended and will be progressed as per availability of resources.
6 Luni-Marwar NR 111.13 110.14 The work has been completed. & Jodhpur- Financial adjustments are being Luni made.The residual work of block proving with axle counters is in progress and will be completed in 2001-02.
7 Luni-Barmer- NR 240.00 36.41 Earthwork between Luni-Samdari (50 Munabao km) has been completed and is in progress between Samdhari and Barmer. 61 minor bridges out of 104 have also been completed and 3 out of 9 major bridges also completed. Ballast collection is in progress. 2.1 lakh cum out of 6.25 lakh cum ballast has been received.
8 Rewari- NR 197.76 0.00 The work will be taken up after the Sadulpur necessary clearances have been obtained.
9 Sriganganagar NR 68.71 0.00 The work will be taken up after the -Sarupsar necessary clearances have been obtained.
10 Agra- WR 169.30 4.51 Earthwork and bridges are in Bandikui progress. 42 minor bridgesout of 193 nos, substructure of 4 major bridges out of 9nos. have been completed and 1.3 lacs cum earthwork out of 3.07 lac cum has been completed.The work is being progressed as per availability of resources.
11 Ajmer- WR 445.38 9.97 The work is in progress between Udaipur- Udaipur and Chittaurgarh in first Chittaurgarh phase.3.65 lac cu.m. of Earthwork has been completed out of 17.41 lac cum,substructure of 72 minor bridges have been completed and other 15 bredges out of the total 204 minor bridges is in progress. Out of total of 8 major bridges,one has been completed in all respect and substructure of 4 more bridges have been completed. The work is being progressed as per availability of resources.
12 Phulera- WR 668.15 616.15 Work has been completed and Marwar- commissioned. Residual works are in Ahmedabad progress. Doubling
13 Kota-Gurla WR 11.70 11.60 The work has been completed and Chambal commissioned. bridge
APPENDIX - II APPENDIX REFERRED TO IN REPLY TO PARTS (a) TO (c) OF LOK SABHA UNSTARRED QUESTION NO. 294 FOR 22.02.2001 S. Name of the Plan-Head Railway Kms. Status
No. Project On-going Railway Surveys in Rajasthan
1 Jaipur to Merta Doubling Northern 219 Yet to be taken up. Rd Target Date of Completion is 31.3.2002
2 Delhi-Ahmedabad Doubling Western 934 In progress Target Date of Completion is 31.10.2001
3 Udaipur City- Gauge Western 346 In progress. Himmatnagar- Conversion Target Date of Ahmedabad Completion is 30.9.2001
4 Anupgarh to New Line Northern 155 Yet to be taken up Bikaner Target Date of Completion is 31.5.2002.
5 Churu to New Line Northern 42 In progress. Taranagar Target Date of Completion is 31.7.2001
6 Jalore-Falna New Line Northern 70 In progress. Target Date of Completion is 31.3.2001
7 Jhunjhunu- New Line Northern 20 In progress. Pilani Target Date of Completion is 31.7.2002
8 Kolayat-Pokaran New Line Northern 260 In progress. Barmer Target Date of Completion is 31.3.2001
9 Merta City to New Line Northern 65 Yet to be taken. Beawar Target Date of Completion is 28.2.2002
10 Nokha-Sikar via New Line Northern 180 In progress. Bedasar and Target Date of Sujangarh Completion is 31.5.2001.
11 Dungarpur to New Line Western 200 In progress Target Ratlam via Date of Completion Banswara is 30.9.2001
12 Jaisalmer to New Line Western 600 In progress. Kandla Target Date of Completion is 31.12.2001