(a) the present status of new line project on Wadsa-Gadchiroli section;
(b) the details of funds allocated for the project; and
(c) the time by which work on the said project is likely to be started/completed?
(a) the present status of new line project on Wadsa-Gadchiroli section;
(b) the details of funds allocated for the project; and
(c) the time by which work on the said project is likely to be started/completed?
MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI K.H.MUNIYAPPA)
(a): Final Location survey of the project has been taken up.
(b): Rs. 1.00 Crore has been allotted for 2012-13.
(c): Preliminary activities on the project have already started. Time frame for completion has not been fixed as projects are being progressed as per the availability of resources.