Question : WADSA GADCHIROLI LINE



(a) the present status of new line project on Wadsa-Gadchiroli section;

(b) the details of funds allocated for the project; and

(c) the time by which work on the said project is likely to be started/completed?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI K.H.MUNIYAPPA)

(a): Final Location survey of the project has been taken up.

(b): Rs. 1.00 Crore has been allotted for 2012-13.

(c): Preliminary activities on the project have already started. Time frame for completion has not been fixed as projects are being progressed as per the availability of resources.