Question : OPEN CAST MINE PROJECT IN ORISSA



(a) whether the Government have sanctioned Chendipara Open Cast Mine Project in Orissa;

(b) if so, the cost thereof;

(c) the details in regard to the employment potentiality thereof; and

(d) the time by which the project is likely to be completed?

Answer given by the minister


MINISTER OF STATE FOR COAL (SHRI N.T.SHANMUGAM)

(a) to (d) : Board of Directors of Mahanadi Coalfields Ltd , under the powers delegated to it , has sanctioned Chendipara Open Cast Mine Project in Orissa at a capital cost of Rs. 19.75 crores. As per sanctioned Project Report , manpower requirement is 220 . The project is scheduled to be completed by March , 2002.