(a) whether first unit of Rajasthan Atomic Power Scheme (RAPS), Rawatbhata,
has not been producing power since October, 2004 ;
(b) if so, the reasons therefor;
(c) the time by which production is likely to start;
(d) the steps being taken by the Union Government to compensate Rajasthan for
the loss of power due to the permanent closure of first unit ;
(e) whether the State Government has requested to increase the allotment for
third to sixth unit of RAPS ;
(f) if so, the details thereof; and
(g) the steps being taken by the Union Government on the request of Rajasthan ?