THE MINISTER OF STATE (INDEPENDENT CHARGE) OF THE MINISTRY OF POWER
(SHRI JYOTIRADITYA M. SCINDIA)
(a) & (b) : Under Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), the
projects are to be executed on turnkey basis by the Implementing Agencies
who award the contracts to the contractors. The performance of Central Public
Sector Undertakings (CPSUs) viz. Powergrid Corporation of India Limited
(PGCIL), National Hydro-electric Power Corporation (NHPC), National Thermal
Power Corporation (NTPC) and Damodar Valley Corporation (DVC) and the
progress achieved during 11th Plan Period is as under:-
CPSUs 11th plan
Un/de-electrified villages BPL households
Coverage Achievement(as Percentage Coverage Achievement(as Percen on 30.11.2012) with respect on 30.11.2012) -tage with to coverage respect to coverage
PGCIL 8535 8246 97% 2441214 2113562 87 %
NHPC 5774 5573 97% 1555540 1350826 87%
NTPC 11470 11245 98% 2564147 2236262 87%
DVC 3598 3244 90% 344149 226183 66%
The State-wise coverage and achievement under RGGVY during
11th Plan Period in respect of all the four CPSUs, is at Annex.
(c) & (d) : Under RGGVY, High Voltage Distribution System (HVDS) has been
envisaged. Under HVDS, instead of one large capacity transformer, a number
of small capacity transformers have been sanctioned to reduce the chances of
power theft and overall Aggregate Technical and Commercial (AT&C) losses.
Adequate transformation capacity as per RGGVY guidelines has been provided
to cover the proposed number of Below Poverty Line (BPL) and Above Poverty
Line (APL) families in the Detailed Project Reports (DPRs) submitted by
Implementing Agencies.