Question : North East Special Infrastructure Development Scheme

(a) whether the work under the North East Special Infrastructure Development Scheme (NESIDS) is under progress;
(b) if so, the details thereof;
(c) the details of the progress and intention of the Government under NESIDS;
(d) the steps being taken by the Government for water supply, electricity and connectivity under physical infrastructure project;
(e) the provision made by the Government to promote tourism; and
(f) the details of the progress made in education and health sector?

Answer given by the minister

The Minister of State (Independent Charge) of the Ministry of Development of North Eastern Region
[Dr. Jitendra Singh]

(a) to (f) The broad objective of North East Special Infrastructure Scheme (NESIDS) is to ensure focused development of North East Region by providing financial assistance for projects of physical infrastructure relating to water supply, power and connectivity to enhance tourism and social sectors for creation of infrastructure in the areas of primary and secondary sectors of education and health. Under NESIDS, 59 projects costing Rs.1835.35 crore have been sanctioned, against which Rs.439.19 crore have been released so far. All the sanctioned projects under the scheme are at various stages of implementation. The sector-wise details of projects sanctioned under NESIDS are as under:

(Rs. in crore)
<pre>
S. No State Sector
Connectivity Power Water Supply Education Health Total
No. Cost No. Cost No. Cost No. Cost No. Cost No. Cost
1. Arunachal Pradesh 10 216.58 0 0.00 5 121.31 3 36.33 0 0.00 18 374.21
2. Assam 4 344.28 0 0.00 3 90.76 0 0.00 1 22.99 8 458.04
3. Manipur 2 45.80 0 0.00 4 112.97 1 3.09 2 32.97 9 194.83
4. Meghalaya 2 45.46 1 49.80 2 59.55 0 0.00 1 20.00 6 174.81
5. Mizoram 2 33.03 1 40.34 1 114.20 0 0.00 0 0.00 4 187.57
6. Nagaland 7 153.71 0 0.00 2 24.04 0 0.00 0 0.00 9 177.75
7. Sikkim 2 103.31 0 0.00 0 0.00 0 0.00 0 0.00 2 103.31
8. Tripura 2 43.95 1 120.88 0 0.00 0 0.00 0 0.00 3 164.83
Total 31 986.12 3 211.02 17 522.83 4 39.42 4 75.96 59 1835.35
</pre>