Question : Increase in Silo Capacity

(a) the total quantum of food grains available in storages across the country as on date;

(b) the details and the number of silo sites that are in development, including the current status of each site, respective estimated storage capacity, and estimated date of completion; and

(c) the progress made as on date towards the goal of doubling India’s silo capacity under public-private partnership by 2019-29 to 15 lakh tonnes?

Answer given by the minister

A N S W E R
MINISTER OF STATE FOR MINISTRY OF RURAL DEVELOPMENT AND
CONSUMER AFFAIRS, FOOD & PUBLIC DISTRIBUTION
(SADHVI NIRANJAN JYOTI)

(a): The total stock of foodgrains held in Central Pool with Food Corporation of India (FCI) as on 1st July 2022 is as given below:
(Figures in Lakh MT)
Wheat Rice (including un-milled Paddy in terms of Rice) Coarse Grains Total
285.10 472.18 3.96 761.24

(b) & (c): In order to upgrade and modernize the storage facilities, Government of India has chalked out an Action Plan for construction of steel silos on Public Private Partnership (PPP) mode in the country. Till date Silos with capacity of 29.25 LMT at various locations throughout country have been awarded. Out of which a capacity of 12.25 LMT is complete and remaining is under various stages of development. In addition, a capacity of 5.5 LMT has been created under circuit based model in 2007. Further, silo capacity of 111.125 LMT in PPP mode is proposed in a phased manner under Hub & Spoke model, out of which capacity of 34.875 LMT has been tendered. The site-wise list of developing Silos across the country is Annexed.
*****
Annexure

ANNEXURE REFERRED TO IN REPLY TO PART (b) & (c) OF THE UNSTARRED QUESTION NO.1706 FOR ANSWER ON 27.07.20222 IN THE LOK SABHA.

STATUS OF RAILWAY SIDING SILOS UNDER IMPLEMENTATION
S. No. Location State Agency (FCI/ State Govt) Capacity (MTs) Status Likely date of completion
1. Katihar Bihar FCI 50000 Completed 01.04.2021
2. Ahmedabad Gujarat FCI 50000 Completed 06.05.2021
3. Jind Haryana FCI 50000 Completed 13.04.2021
4. Sonepat Haryana FCI 50000 Completed 13.04.2021
5. Bhattu* Haryana FCI 50000 Completed 29.04.2021
6. Panipat* Haryana FCI 50000 Completed 13.04.2022
7. Harda Madhya Pradesh State Govt 50000 Completed 2017-18
8. Hoshangabad Madhya Pradesh State Govt 50000 Completed 2017-18
9. Dewas Madhya Pradesh State Govt 50000 Completed 2017-18
10. Satna Madhya Pradesh State Govt 50000 Completed 2017-18
11. Sehore Madhya Pradesh State Govt 50000 Completed 2017-18
12. Ujjain Madhya Pradesh State Govt 50000 Completed 2017-18
13. Vidisha Madhya Pradesh State Govt 50000 Completed 2017-18
14. Bhopal Madhya Pradesh State Govt 50000 Completed 2017-18
15. Indore Madhya Pradesh State Govt 50000 Completed 2017-18
16. Patiala* Punjab FCI 50000 Completed 14.06.2019
17. Sangrur* Punjab FCI 100000 Completed 14.06.2019
18. Barnala Punjab FCI 50000 Completed 01.03.2020
19. Kotkapura Punjab FCI 25000 Completed 30.09.2017
20. Sunam Punjab State Govt 50000 Completed 2017-18
21. Malerkotla Punjab State Govt 50000 Completed 2017-18
22. Ahmedgarh Punjab State Govt 50000 Completed 2017-18
23. Changsari Assam FCI 50000 Completed 18.09.2021

.......2/-

-2-
24. Kannauj* Uttar Pardesh FCI 50000 Completed 31.03.2022
A Total 1225000
25. Darbhanga Bihar FCI 50000 Under Construction
05.05.2023
26. Khagaria Bihar FCI 50000 Under Construction 05.05.2023
27. Kaimur Bihar FCI 50000 Under Construction 30.10.2022
28. Buxar Bihar FCI 50000 Under Construction 30.10.2022
29. Palanpur&Siddhpur Gujarat FCI 50000 Under Construction 30.06.2023
30. Amreli Gujarat FCI 50000 Under Construction 06.12.2022
31. Baroda Gujarat FCI 50000 Under Construction 31.12.2022
32. Rohtak Haryana FCI 50000 Under Construction 31.08.2022
33. Batala Punjab FCI 50000 Under Construction 31.08.2022
34. Chhehreata Punjab FCI 50000 Under Construction 31.08.2022
35. Jalalabad Punjab FCI 50000 Under Construction 31.03.2023
36. Sahnewal Punjab FCI 50000 Under Construction 31.05.2023
37. Basti Uttar Pradesh FCI 50000 Under Construction 31.08.2022
38. Deoria Uttar Pradesh FCI 50000 Under Construction 31.12.2022
39. Faizabad Uttar Pradesh FCI 50000 Under Construction 31.12.2022
40. Fatehpur Uttar Pradesh FCI 50000 Under Construction 31.03.2023
41. Gorakhpur Uttar Pradesh FCI 50000 Under Construction 30.06.2023
42. Lucknow Uttar Pradesh FCI 50000 Under Construction 30.06.2023
43. Dhamora Uttar Pradesh FCI 50000 Under Construction 30.06.2022
44. Malda West Bengal FCI 50000 Under Construction 31.03.2023
45. Bhagalpur Bihar FCI 50000 Under Construction 31.03.2023
46. Samasthipur Bihar FCI 50000 Under Construction 31.07.2022
47. Madhubani and Benipatti
Sub-divisions Bihar FCI 50000 Under Construction 30.10.2022
48. Balurghat West Bengal FCI 50000 Under Construction 30.04.2024
49. Hamirpur Uttar Pradesh State Govt 50000 Under Construction 30.04.2024

.........3/-


-3-

50. Pilibhit Uttar Pradesh State Govt 50000 Under Construction 30.04.2024
51. Madhepura Bihar FCI 50000 Under Implementation LoC not issued
52. Motihari Bihar FCI 50000 Under Implementation LoC not issued
53. Saran Bihar FCI 50000 Under Implementation LoC not issued
54. Lalitpur
Uttar Pradesh State Govt 50000 Under Implementation LoC not issued
55. Murshidabad West Bengal FCI 50000 Under Implementation LoC not issued
56. Durgapur West Bengal FCI 50000 Under Implementation LoC not issued
57. Dankuni West Bengal FCI 50000 Under Implementation LoC not issued
58. Harduaganj Uttar pradsh FCI 50000 Under implementation LoA issued (30.06.2022)
B Total 17,00,000
Total (A+B) 29,25,000
*Operationalization has commenced without railway siding
*****