MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI BANDARU DATTATRAYA )
(a) to (c) : A memorandum was submitted by the Chief Minister
of Kerala to the Ministry of Railways in December, 2001 in
respect of projects/works in Kerala. Demands contained in the memorandum and action taken
on them are at Appendix.
APPENDIX
APPENDIX REFFERED TO IN REPLY TO PARTS (a) TO (c) OF LOK SABHA
UNSTARRED QUESTION NO. 2774 FOR 01.08.2002
POSITION OF POINTS RAISED IN THE MEMORANDUM PRESENTED BY CHIEF
MINISTER, KERALA TO MINISTRY OF RAILWAYS IN DECEMBER, 2001
S. Projects / Works Action Taken
No.
New Railway Lines
1. Angamali-Sabarimala The work is already included in the Budget. Final location survey is in progress. An outlay of Rs.10 crore has been provided for the work during 2002-03.
2. Kottayam-Erumeli The work has already been included in the Budget and necessary clearances have been obtained. Final location survey and detailed planning has been taken up. An outlay of Rs.0.01 crore has been provided for the work during 2002-03.
3. Kuttipuram- The work is already included in the
Guruvayoor Budget and will be taken up after obtaining necessary clearances for which action has been initiated.
Doubling of Railway Lines
1. At least Rs. 150 Doubling of single line is taken up
crores for doubling when the carrying capacity of the line
of Mulanturutti- is saturated, keeping in view the
Kayankulam(via traffic requirement. The doubling of
Kottayam) railway Ernakulam-Mulanturutti has been taken
line during 2002-03 up as phase-I of doubling of Ernakulam-Kayankulam. The work is in progress and an outlay of Rs.3.68 crore has been provided during 2002-03. The doubling of remaining section may be considered in future as and when the need arises.
2. Doubling of The doubling is not considered
Ernakulam- necessary at present from traffic point
Kayankulam (via of view.
Alapuzha)
New Railway Stations/facilities
1. New Railway Station A new Railway station at Nedumbasseri
at Nedumbassery near Cochin is not considered necessary at this stage.
2. Satellite Railway The work of 2nd Coaching Terminal at
Station at Kochuveli has been included in the
Trivandrum - Rs. 10 Budget 2002-03.
crores for 2002-03
Other Projects
1. Crossing station at The crossing station is not considered
Mavelikkara- justified.
Chengannur - 5
crore
2. Crossing station at Parsala included in the budget 2002-03
Parasala-Nemom but Nemom was not considered justified from traffic point of view.
Adequate Funding for Ongoing Works
1. Early completion of On Mangalore-Shoranur section, out of
ongoing doubling 307 km, doubling of 161 km has already
works: (Rs.125 been completed. 50 km is targeted for
crores) 2002-03 and balance for 2003-04.
Mangalore-Shoranur Regarding Ernakulam-kayankulam remarks
line (committed have already been given at point no.2
target dated 31-03- of Doubling plan head.
2003)
Ernakulam-
Kayankulam (via-
Kottayam) (Rs.50
crores)
Electrification (30 Crores)
1. Ernakulam- The work is in progress.
Trivandrum BG line,
by 31-03-2004
Gauge Conversion (10 Crores)
1. Quilon-Shenkottai- The work is in progress. Final
Virudunagar (357 location survey in the ghat section has
km) been completed. Earthwork and bridges have been taken up on Tenkasi- Virudunagar and Tirunelveli-Tiruchchendur section. An outlay of Rs.25 crore has been provided for this work during 2002-03.
New Trains
1. The weekly Examined, but not found feasible due to
Thiruwanthapuram- operational and resource constraints.
Mangalore-
Thiruwanthapuram
Express via
Alappuzha may be
converted as daily.
2 A new daily train Examined, but not found feasible due to
may be introduced operational and resource constraints.
in the sector
Mumbai-Kozhikode.
3 Electric Trains on Examined, but not found feasible due to
Thrissur-Ernakulam operational and resource constraints.
sector.