MINISTER OF RURAL DEVELOPMENT
(SHRI GIRIRAJ SINGH)
(a) & (b) A Statement is laid on the Table of the House.
Statement referred to in reply to Parts (a) to (b) of Lok Sabha Starred Question No. 472 due for answer on 05.04.2022
(a) Valmiki Nagar Parliamentary Constituency is a part of West Champaran district of Bihar. The district-wise details of road length constructed under PMGSY in the state of Bihar during the last three years and the current year (as on 30.03.2022) (including that under Valmiki Nagar Parliamentary Constituency) are given in the Annexure.
(b) The details of balance works under PMGSY (PMGSY-I, II, III) & RCPLWEA as on 30.03.2022 in the state of Bihar and West Champaran district are as under:-
Bihar
Intervention Balance
No. of Roads Road length (km) No. of Bridges
PMGSY-I 408 1,007 273
PMGSY-II 67 144 58
RCPLWEA 68 533 45
PMGSY-III 169 1,390 39
West Champaran District
Intervention Balance
No. of Roads Road length (km) No. of Bridges
PMGSY-I 3 3 0
PMGSY-II 1 99 0
PMGSY-III 9 73 3
The timeline for completion of PMGSY-I & II is September, 2022 and for RCPLWEA, it is March 2023. The target road length allocated to the state of Bihar under PMGSY-III is 6,162.50 km, against which 1,390.31 km has been sanctioned to the state till 30.03.2022. The timeline for completion of PMGSY-III is March, 2025.
******