Question : REPAIR OF TRANSMISSION TOWERS



(a) whether the Nepal Government has requested for early repair of transmission towers uprooted during the recent Kosi floods to restore power supply from India;

(b) if so, the details thereof; and

(c) the steps taken by the Government in this regard?

Answer given by the minister


THE MINISTER OF STATE IN THE DEPARTMENT OF COMMERCE, MINISTRY OF COMMERCE & INDUSTRY AND MINISTER OF STATE IN THE MINISTRY OF POWER ( SHRI JAIRAM RAMESH )

(a) & (b) : Yes, Sir. The Government of Nepal has requested for restoration of Forbesganj-Kataiya Section of Transmission Line in Bihar by mid-February, 2009. There are two transmission lines
(i) 132 kV Katiya-Forbesganj Circuit-I and
(ii) 132 kV Katiya-Forbesganj Circuit-II of the Bihar State Electricity Board (BSEB) from which power is fed to Nepal. These lines had collapsed due to the devastating floods in Kosi river.

(c) : The Government of India had taken up the issue with the Government of Bihar for early restoration of these transmission lines. The Government of Bihar have intimated that work has started on Circuit-II line and this line would be available for feeding power to Nepal by the end of February, 2009. The restoration of Circuit-I would be taken up by Bihar State Electricity Board subsequently.