MINISTER OF THE STATE IN THE MINISTRY OF COMMUNICATIONS AND INFORMATION TECHNOLOGY (SHRI A.RAJA)
(a) to (e) A statement is laid on the Table of the House.
STATEMENT TO BE LAID ON THE TABLE OF THE LOK SABHA IN RESPECT OF PARTS (a) TO (e) OF
THE LOK SABHA STARRED QUESTION NO. 438 FOR 26TH APRIL, 2010 REGARDING âMOBILE TOWERSâ.
(a) & (b) As per the existing procedure for installation of towers, Wireless Planning and Coordination
(WPC) Wing of Department of Telecommunications (DoT) issues siting clearance for installation of mobile
towers for each and every site from the point of view of interference with other wireless users, aviation
hazards and obstruction to any other existing microwave links.
However, apart from above permission from DoT for establishment of towers, the licensee company is also
required to obtain the permission from the concerned local bodies/authorities in terms of Section 10 (c)
and12 of Indian Telegraph Act, 1885.
Accordingly, while issuing siting clearances, WPC Wing directs the service providers to obtain necessary
clearances from concerned local authorities/Municipal Corporations/Gram Panchayat etc. However, grant of
such permissions are not being conveyed by local bodies/authorities to DoT.
(c) No, Madam.
(d) & (e) Question does not arise in view of (c) above.