Question : Watershed Development Projects

LOK SABHA
UNSTARRED QUESTION No. 288
TO BE ANSWERED ON 30.11.2021

Watershed Development Projects

288 SHRI VENKATESH NETHA BORLAKUNTA:
SHRI PASUNOORI DAYAKAR:
DR. G. RANJITH REDDY:
SHRIMATI KAVITHA MALOTHU

Will the Minister of Rural Development be pleased to state:
(a) whether it is true that 330 watershed development projects have been sanctioned for Telangana under PM Krishi Sinchayee Yojana, if so, the details thereof;

(b) whether it is true that more than 200 projects are pending for completion, if so, details thereof, district-wise;

(c) the reasons for delay in completing the projects and efforts being made by the Ministry to complete the left out projects; and

(d) the details of amount so far spent on the above projects, district-wise?

Answer given by the minister

ANSWER
MINISTER OF STATE IN THE MINISTRY OF RURAL DEVELOPMENT
(SHRI FAGGAN SINGH KULASTE)

(a) to (d) The Department of Land Resources (DoLR) has sanctioned 330 watershed development projects to Telangana covering an area of about 13.99 lakh hectare during the period 2009-10 to 2014-15 under the erstwhile Integrated Watershed Management Programme (IWMP). Subsequently IWMP was amalgamated as a Watershed Development Component of Pradhan Mantri Krishi Sinchayee Yojana (WDC-PMKSY) in 2015-16. A total number of 54 projects in preparatory stage were transferred to State in 2018 to implement them from their own budget. Therefore, DoLR has been financially supporting only 276 projects in State of Telangana.

Out of these, 276 projects, 191 projects have been reported as completed by State of Telangana. Remaining 85 projects are in advanced stage of completion.

Due to uncertainty posed by the pandemic COVID-19, State has not been able to complete planned activities. The State has got Rs. 67.26 crore unspent balance (as on 06.11.2021) which will be utilized for the completion of these projects by March, 2022. DoLR is regularly reviewing the progress of implementation of the scheme with Telangana. D.O. letters to Chief Secretary / Secretary have been written. Video Conferences with CEO, State Level Nodal Agency (SLNA), their officers and field visits to State by Senior Officers of the Department are also undertaken. During these reviews, completion of these projects have always being emphasized.
As per information received from State of Telangana, the district-wise details of projects sanctioned, projects completed and funds spent is given at Annexure.

*****



Annexure

Annexure referred to in reply to part (a) to (d) of Lok Sabha Unstarred Question No. 288 for answer on 30.11.2021

District-wise details of number of projects, sanctioned, completed and funds spent for the projects in Telangana

Sl. Districts No of Projects No of projects Funds spent
No. sanctioned completed (Rs. in lakh)

1 Adilabad 22 10 7572.2
2 Bhadradri Kothagudem 19 6 5027.37
3 Jangaon 3 0 230.59
4 Jogulamba Gadwal 12 9 2022.38
5 Khammam 7 1 1092.94
6 Kumaram Bheem Asifabad 19 10 6435.89
7 Mahabubabad 18 11 366.26
8 Mahabubnagar 3 0 4386.94
9 Mancherial 11 7 3147.13
10 Medak 11 5 3483.71
11 Mulugu 7 0 648.91
12 Nagarkurnool 30 18 6482.2
13 Nalgonda 29 22 8701.69
14 Narayanpet 15 8 2669.32
15 Nirmal 7 6 2414.09
16 Rajanna Sirsilla 1 0 0.09
17 Rangareddy 28 19 6826.43
18 Sangareddy 20 17 6490.01
19 Siddipet 9 3 1520.32
20 Suryapet 8 7 2366.91
21 Vikarabad 25 17 8974.77
22 Wanaparthy 12 9 2582.85
23 Hanamkonda 2 0 3.95
24 Warangal 1 0 354.3
25 Yadadri Bhuvangiri 11 6 1815.97
----------------------------------------------------------------------------------
Total 330* 191 85617.22
----------------------------------------------------------------------------------
* Includes 4 projects which were transferred to Andhra Pradesh during the process of bifurcation of Andhra Pradesh and Telangana.


*****