THE MINISTER OF STATE FOR PLANNING AND PARLIAMENTARY AFFAIRS (SHRI V. NARAYANASAMY) :
(a) to (e) The Environmental Impact Assessment of the project was conducted by National
Environmental Engineering Research Institute (NEERI). In addition, Bombay Natural History
Society (BNHS) have submitted a detailed bio-diversity assessment report of the region. The
Central Water and Power Research Station has carried out model studies for temperature rise
of the cooling water. All objections/ criticisms of the reports have been given due
consideration by the Expert Appraisal Committee (EAC) of the Ministry of Environment & Forest
(MoE&F) for strategic projects. MoE&F have after detailed consideration of the reports and
the objections thereto have accorded Environmental Clearance for the project subject to certain
conditions. This inter alia, include preparation of a comprehensive bio diversity plan,
constitution of a monitoring committee, reinforcement of environmental stewardship programme
of NPCIL and clearances by the Atomic Energy Regulatory Board. The conditions stipulated by
MoE&F shall be adhered to.