Question : POWER PLANTS IN RAJASTHAN



(a) the capacity of power plants in Rajasthan in different sectors;

(b) the details of power generated, demanded and supplied to the State at present; and

(c) the steps taken or proposed to be taken by the Union Government to improve the power situation in Rajasthan?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF POWER ( SHRIMATI JAYAWANTI MEHTA )


(a) & (b) : The details of monitored capacity of power plants in Rajasthan in different sectors/categories and power generated during October, 2002 are given below :

October, 2002
Sector Thermal Hydro Nuclear Total Cap Gen. Cap Gen Cap. Gen. Cap. Gen. (MW) (MU) (MW) (MU) (MW) (MU) (MW) (MU)
Central 413 258 - - 790 409 1203 667 State 1926 1196 430 5 - - 2356 1201
Total 2339 1454 430 5 790 409 3559 1868
Power supply position in the State during the month of October, 2002 is given below :-
Energy (MU) Peak (MW)
Requirement 2272 Peak Demand 3716 Availability 2258 Peak met 3716 Shortage 14 Deficit 0 Percentage 0.6 Percentage 0



(c) : The following steps have been taken/being taken for augmentation of availability of power in the country including Rajasthan :


(i) Maximizing generation from existing capacity.


(ii) Demand side management.


(iii) Reduction in T&D losses.


(iv) Energy conservation measures.


(v) Renovation & Modernisation and Life Extension of old and inefficient plants.


(vi) Enhancement of inter-regional exchange of power from surplus region/states to deficit states.


(vii) Early stabilization of ongoing projects.


(viii) It is envisaged to add 660.32 MW in Rajasthan in State Sector during 10th Plan period. In addition the state will also get its due share from the central generating stations (7340 MW) which are proposed to be set up in Northern Region during 10th Plan.