Question : RAIL PROJECTS IN KERALA



(a) the number of new rail lines, doubling, gauge conversion electrification railway bridges foot over bridges platform arrangements, modernization conversion of meter gauge to broad gauge being undertaken/proposed to be undertaken in Kerala;

(b) if so, the amount allocated for each during the current financial year; and

(c) the estimated period of completion of the each project?

Answer given by the minister

MINISTER OF STATE IN THE MINISTRY OF RAILWAYS ( SHRI R. VELU )

(a) to (c): A statement is attached.

STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF UNSTARRED QUESTION NO.1578 BY SHRI M.P. VEERENDRAKUMAR TO BE ANSWERED IN LOK SABHA ON 09-12-2004 REGARDING RAILWAY PROJECTS IN KERALA.

(a) to (c): The details of ongoing new lines, gauge conversion, doubling and electrification projects falling partly/fully in the State of Kerala along with the estimated cost, outlay provided during 2004-05, expenditure incurred till 31-03-04 and the target, wherever fixed, are as under:-

(Rupees in crores)
Sl Name of	Estimated	Exp.	Outlay	Status
No. Project Cost	upto,	2004-05	March	2004 NEW LINE
1. Tanur(Kuttipu 137.71 6.72	3	Survey work has ram)-	stopped due to Guruvayur	local	agitations. The	matter is being	pursued with	the State	Government for	land	acquisition. No	land is made	available to	the Railways.
2. Angamali- 550 5.40	2	The matter is Sabarimala	being pursued	with the State	Government for	land	acquisition. No	land is made	available to	the Railways.
3. Kottayam- 200 0.14	2	Survey work has Erumeli	stopped due to	local	agitations. The	matter is being	pursued with	the State	Government for	land	acquisition. No	land is made	available to	the Railways. GAUGE CONVERSION
1. Quilon- 462.61 137.70	21.06	Virudhunagar- Tirunelveli-	Tenkasi Tiruchendur	converted line and Tenkasi-	has been Virudhunagar	commissioned.	On Tirunelveli-	Tiruchendur and	Quilon-Punalur	section, works	are in various	stages of	progress.	Final location	survey report	on the Ghat	section between	Sengottai and	Punalur is	being	finalized. DOUBLINGS
1. Calicut- 583.74 502.28	15	Work has been Mangalore	completed (221 kms)	except at	Naitravati	bridge where	works are in	progress.
2. Shoranur- 178.23 82.92	30	Land Calicut (86	acquisition, km)	earthwork and	bridges are in	progress. 30 km	doubling is	targeted for	completion	during 2003-04.
3. Ernakulam- 53.23 16.70	8	Earthwork, Mulanturutti	bridgeworks and (17.37 km)	other works are	in progress.	The work is	likely to be	completed by	2005-06.
4 Kayankulam- 21.84 3.83	2.34	Land Mavelikkara	acquisition (7.89 km)	papers	submitted to	State	Government.	Work on major	bridge has	started.
5 Kayankulam- 21.48 3.34	2	Final location Cheppad (7.76	survey km)	completed.	Land	acquisition	papers	submitted to	State	Government.
6 Mavelikkara- 33.65 0	2	New work Chengannur	included in (12.3 km)	Supplementary	Demand for	Grants 03-04.	Preliminary	works taken up.
7 Cheppad- 14.39 0	2	New work Haripad (5.28	included in km)	Supplementary	Demand for	Grants 03-04.	Preliminary	works taken up. RAILWAY ELECTRIFICATION
1. Ernakulam- 162.32 106.71	37.92	102 route km Trivandrum	has already (320 km)	been	electrified	upto March 2004	and balance by	December, 2005.



A survey for doubling of Trivandrum-Kanniyakumari and updating surveys for doubling of balance section of Kayankulam-Ernakulam via Kottayam/Alleppey and construction of new rail line from Erumeli to Trivandrum via Punalur are in progress. Further consideration of these proposals could be possible once the survey reports become available.

Status of bridges is maintained Railway-wise not State-wise. There are total 354 bridges sanctioned as on 1.4.2004 on Southern Railway which serves the Kerala State also. In the current financial year Rs. 39.21 crores has been allotted in the budget estimate for execution of ongoing works over Southern Railway. Out of 354 bridges, 62 bridges are targeted for completion in the current financial year. Remaining bridges are in the various stages planning and execution and planned to complete upto 2006-07.

Indian Railways have more than 8000 stations. The works of provision of Foot over bridges, platforms arrangements and modernization of stations are taken up as per norms based on actual passenger traffic needs at the station, inter-se priorities and availability of funds. State-wise position is not maintained. Kerala falls in Southern Railway and the details of Foot over Bridge/platform arrangements/modernization of railway stations sanctioned on Southern Railway are included in the “Works Machinery and Rolling Stock Programme, Part-II” presented to the Parliament along with the Railway Budget Documents.