MINISTER OF STATE IN THE MINISTRY OF COAL
(SHRI PRATIK PRAKASHBAPU PATIL)
(a) to (d): The names of the public and private companies to
whom coal and lignite blocks have been allocated alongwith the
date of allotment, location and quantum of coal reserves assessed
in these blocks, State-wise including the status as to producing or
non-producing are given at Annexure-I.
The responsibility of developing the coal block as per the prescribed
guidelines and milestone chart attached with the allocation letter
rests entirely with the allocattee company. In the terms and
conditions of the allocation letters, it is categorically mentioned
that in the event of willful delay in the development of coal blocks
and in setting up of the end use project, the Govt. takes appropriate
action to de-allocate the said block. Further, the allocatees have
to submit Bank Guarantee which remains valid all the times till the
production from the coal block reaches its peak rated capacity. The
State Govts. have been requested to form a Monitoring Committee headed
by the Chief Secretary to facilitate expeditious development of coal/
lignite blocks. The Coal Controllerâs office monitors on regular basis
the achievement of different milestones. Government periodically monitors
and reviews the development of allocated blocks as well as end use
plants by the allocattee companies in the Review Meetings. Wherever
delays are noticed, Government issues show cause notices and advisories
to such allocattees cautioning them to bring the coal blocks into
production as per the guidelines/milestones chart. Based on the
replies to the show cause notices, the Government takes decision
on the de-allocation. A total of 25 coal blocks and 2 lignite
blocks were de-allocated. State-wise and company-wise details
of de-allocated blocks are at Annexure-II.
Out of 195 coal blocks, 29 coal blocks have started production. Further
out of the 28 allocated lignite blocks, 12 lignite blocks have started
production. The remaining coal blocks which have not started production
so far, are in various stages of obtaining statutory clearances and mining
lease, preparing mining plan, acquisition of land, procuring machinery
and equipment etc. for both mining as well as end-use project.