Question : COMPLETION OF RAILWAY PROJECTS



(a) whether in the past the Railways had issued white paper with regard to shortage of funds and non-availability of adequate funds for the ongoing projects of Railways;

(b) if so, the details thereof;

(c) whether revenue earnings of the Railways from various sources has increased recently;

(d) if so, the details thereof;

(e) whether the Government proposes to fix priority to complete the pending and ongoing projects of Railways keeping in view the increase in revenue earning of Railways during the recent past; and

(f) if so, the details thereof?

Answer given by the minister


MINISTER OF STATE IN THE MINISTRY OF RAILWAYS (SHRI R. VELU)

(a) to (f) : A Statement is attached.

STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (f) OF UNSTARRED QUESTION NO.4408 BY SHRI HEMLAL MURMU TO BE ANSWERED IN LOK SABHA ON 22.12.2005 REGARDING COMPLETION OF RAILWAY PROJECTS.

(a) & (b): A White Paper on Railway Projects was published in July, 1998 in which the issue of heavy throwforward and availability of inadequate funds for Railway projects was highlighted.

(c) & (d): The overall traffic revenues of the Railways to end of November, 2005, have registered a growth of 13.89% (approximate) over the corresponding period of last year. Segment-wise details are as under:


(Figure: Rupees in crore)
Traffic Segment	Traffic Revenue to end of	November, 2004	November, 2005	%age growth	(Approximate)
Passenger 9279.41 9827.48 5.91% Other Coaching 614.51 694.18 12.96% Goods 19356.70 22881.24 18.23% Sundry 645.00 642.42 -0.40%
Total 29895.62 34045.32 13.89%




(e) & (f): Re-prioritisation of projects has been done recently. Further with the increase in internal generation, it is proposed to revive Capital Fund for funding of some of the critical throughput enhancement works.