THE MINISTER OF THE STATE IN THE MINISTRY OF POWER (SHRI SUSHILKUMAR SHINDE)
(a) & (b) : The following four thermal power stations (T.P.S.) are lying closed
as on date for reasons indicated against each of them:
Sl.No. Name of the Power Station State Reasons for closure and capacity (MW)
1. Barauni Thermal Power Bihar Major R&M/ Refurbishment Station (2x50 +2x110) required.
2. Muzaffarpur Thermal Bihar Major R&M/ Refurbishment Power Station (2x110) required.
3. Chandrapur Thermal Assam Uneconomical operation Power Station (2x30) due to high fuel cost.
4. Bongaigaon Thermal Assam Major R&M/ Refurbishment Power Station (4x60) required.
(c)to(e) : Revival/restoration works in respect of Barauni T.P.S.- 2x110 MW (Unit
6&7) and Muzaffarpur T.P.S.-2x110 MW are in progress. Unit 6 at Barauni and Unit
2 at Muzaffarpur are expected to be revived by March, 2007. Revival/Restoration of
Barauni T.P.S. -2x50 MW (Unit 4&5) is expected in 11th Plan.
Revival/Restoration of Chandrapur T.P.S.-2x30 MW has been found to be
feasible on the availability of natural gas and required modifications in the
unit for gas firing. Revival/restoration of Bongaigaon T.P.S.-4x60 MW units has not
been found to be techno-economically viable.