MINISTER OF THE STATE IN THE MINISTRY OF COAL
(DR. DASARINARAYANA RAO)
(a) to (f): A statement is laid on the Table of the House.
Statement referred to in reply to parts (a) to (f) of the Lok Sabha
Starred Question No.325 for answer on 17.08.2005 regarding Fire at
Jharia Coal Mine.
(a): Total area affected by fire in Bharat Coking Coal Ltd. (BCCL)
as per study conducted by Central Mine Planning and Design Institute
Ltd. (CMPDIL) in 1999 is around 8.9 sq. km., out of the total leasehold
area of about 270 sq. km. Total reserve lost due to fire is estimated at
around 37 million tonnes. 10 fires have been extinguished and the
remaining fires are by and large kept under control.
(b): Total geological reserve in BCCL leasehold area as assessed by
Geological Survey of India (GSI) as on 1.1.2005 upto a depth of 1200
metre is 18.27 billion tonnes. Reserve blocked due to fire/subsidence
caused by fire as estimated in 1995 is approximately 1453 million tonnes.
(c): The following measures are being taken by BCCL to control fire
depending upon -the conditions:
# Blanketing/surface sealing/sealing;
# Sand flushing;
# Inert gas injection;
# Trench cutting;
# Water pooling etc.
(d) to (f): A Master Plan for `Dealing with Fire, Subsidence and
Rehabilitation in the Leasehold of BCCL` has been prepared in April 2004.
The Master Plan envisages rehabilitation of unstable and uncontrollable
subsidence prone habitated areas of Jharia Coalfield. There is no proposal
to relocate the main Jharia town. However, parts of Jharia town adjacent
to surrounding areas have been identified to be shifted due to effect of
fire and subsidence. The total capital outlay of the Master Plan is Rs.
5792.21 crores, out of which the cost of rehabilitation will be Rs. 2446.91
crores (March 2004 base).