Question : Bullet Train Project

(a) the present status of the Bullet Train Project;

(b) whether there has been any cost escalation in the project because of the delays and if so, the details thereof; and

(c) the details of current impediments in the project?

Answer given by the minister

MINISTER OF RAILWAYS AND COMMERCE & INDUSTRY

(SHRI PIYUSH GOYAL)

(a) to (c): Mumbai-Ahmedabad High Speed Rail (MAHSR) Project is being executed by a Special Purpose Vehicle (SPV) namely National High Speed Rail Corporation Limited (NHSRCL), with technical and financial assistance of Government of Japan. The cost escalation compared to the cost indicated in Feasibility Study, if any cannot be ascertained at this stage, as most of the Contract Packages are still to be finalised. The land availability and Statutory clearances regarding Wildlife and Coastal Regulation Zone have been a challenge which have been resolved by regular follow up with State Government and other concerned agencies.

*****