MINISTER OF STATE FOR MINISTRY OF CONSUMER AFFAIRS, FOOD & PUBLIC DISTRIBUTION
(SHRI DANVE RAOSAHEB DADARAO)
(a) to (e): Depending on requirement in specific areas and for modernization of storage facilities, Government implements the following schemes for construction of godowns and silos in the country for central pool stock of foodgrains:
..........2/-
-2-
i. Private Entrepreneurs Guarantee (PEG) Scheme: Under this Scheme, which was formulated in 2008, storage capacity is created by private parties, Central Warehousing Corporation (CWC) and State Government Agencies for guaranteed hiring by Food Corporation of India (FCI). A capacity of 142.62 Lakh MT (LMT) has been created as on 31.05.2019. The State/UT-wise details of capacity created during the last 3 years, current year (up to 31.05.2019) and since inception of the scheme are at Annexure-I. Under this scheme, no funds are allocated by Government for construction of godowns and full investment is done by the private parties/CWC/State Agencies. The time limit for construction of godowns under this scheme is 1 year without railway sidings and 2 years with railway siding. As per the agreement, the responsibility of delay in construction is on the part of investor/private party. The delay in construction of maximum up to one year may be allowed with a clause of similar reduction in the guarantee period. In case of delay beyond one year of the agreement, appropriate decision is taken by State Level Committee (SLC)/High Level Committee (HLC) of FCI. The State/UT-wise status of ongoing projects under PEG Scheme (as on 31.05.2019) is at Annexure-II.
ii. Central Sector Scheme (erstwhile Plan Scheme): This scheme is implemented in the North Eastern States along with a few other States. Funds are released by the Government to FCI and also directly to the State Governments for construction of godowns. A total capacity of 68,995 MT has been completed by FCI and State Governments from 01.04.2016 to 31.05.2019. The State/UT-wise details of capacity constructed under the Scheme are at Annexure-III. The State/UT-wise details of ongoing projects under the scheme are at Annexure-IV. The State/UT-wise funds allocated, released and utilized for construction of godowns during the last 3 years and current year are at Annexure-V. The progress of construction of godowns is monitored and periodically assessed. It is ensured that funds are released only after the State Governments/FCI furnish utilization certificates.
iii. Construction of Steel Silos: In addition to conventional godowns, Government of India has also approved an action plan for construction of steel silos in the country for a capacity of 100 LMT in Public Private Partnership (PPP) mode for modernizing storage infrastructure and improving shelf life of stored foodgrains. Against this, as on 31.05.2019, steel silos of 6.75 LMT capacity have been created. The State/UT-wise details of capacity created during the last 3 years, current year along with the ongoing projects of construction of steel silos are at Annexure-VI. The State/UT-wise details of silos planned in the country as per the action plan/road map approved by Government of India are at Annexure-VII. As per the concession agreement the silos are to be constructed within 2.5 years of signing concession agreement. The Concession Agreement which is signed between Government Agencies and private parties provide for penalties if the projects are delayed beyond the stipulated period. The silos are constructed in PPP mode and investment is done by the private parties. However, in case of silos constructed in Viability Gap Funding (VGF) model, the private party can seek grant in the tender. The grant approved by Ministry of Finance, Government of India for construction of silos in VGF model during the last three years and current year i.e. 2019-20 (up to 31.05.2019) is at Annexure -VIII.
***
Annexure-I
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The State/UT-wise details of the capacity created during the last 3 years, current year and total capacity created since inception of PEG scheme are as given below:
(figures in LMT)
SL State 2016-17 2017-18 2018-19 2019-20
(up to 31.05.2019) Total capacity created since inception
(as on 31.05.2019)
1 Andhra Pradesh 0.00 0.00 0.00 0.00 0.88
2 Bihar 1.07 0.45 0.10 0.15 3.55
3 Chhattisgarh 0.12 0.00 0.00 0.00 5.38
4 Gujarat 0.00 0.00 0.00 0.00 0.50
5 Haryana 0.00 0.00 0.00 0.00 34.37
6 Himachal Pradesh 0.00 0.00 0.00 0.15 0.40
7 Jammu & Kashmir 0.08 0.20 0.07 0.00 1.63
8 Jharkhand 0.15 0.65 0.40 0.15 2.48
9 Karnataka 0.00 0.00 0.00 0.00 2.41
10 Kerala 0.00 0.00 0.00 0.00 0.05
11 Madhya Pradesh 0.95 0.21 0.15 0.00 13.03
12 Maharashtra 0.00 0.00 0.00 0.00 5.63
13 Odisha 0.10 0.20 0.28 0.00 3.52
14 Punjab 0.40 0.00 0.00 0.00 44.68
15 Rajasthan 0.00 0.15 0.00 0.00 2.35
16 Tamil Nadu 0.40 0.55 0.00 0.00 2.55
17 Telangana 0.00 0.00 0.00 0.00 2.69
18 Uttar Pradesh 0.46 1.25 0.36 0.00 14.64
19 Uttarakhand 0.00 0.10 0.00 0.00 0.10
20 West Bengal 0.17 0.05 0.05 0.00 1.54
21 Assam - 0.25 0.00 0.00 0.25
Total 3.90 4.06 1.40 0.45 142.62
****
Annexure-II
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The State/UT-wise details of ongoing projects under construction in Private Entrepreneurs Guarantee (PEG) Scheme (as on 31.05.2019) is as given below:
SL State Capacity (in MT)
1 Uttar Pradesh 41,660
2 Haryana 47,230
3 West Bengal 90,000
4 Bihar 213
5 Odisha 5,000
6 Madhya Pradesh 76,500
7 Andhra Pradesh 25,000
8 Tamil Nadu 10,000
9 Jharkhand 60,000
10 Jammu & Kashmir 86,660
11 Himachal Pradesh 76,700
12 Telangana 50,000
Total 5,68,963
****
Annexure-III
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The State-wise capacity of construction of godowns under Central Sector (erstwhile plan) Scheme from 2016-17 to 2019-20 (upto 31.05.2019) by FCI is as below:-
(Capacities in MT)
SL State 2016-17 2017-18 2018-19 2018-19 (upto 31.05.2019) Cumulative capacity completed from 01.04.2016 to 31.05.2019
1 2 3 4 5 6 7
1 Assam - - - - -
2 Arunachal Pradesh 3,980 3,340 - - 7,320
3 Manipur - - 17,100 - 17,100
4 Meghalaya - - - - -
5 Mizoram - - - -
6 Nagaland - 4,590 - - 4,590
7 Sikkim - - - -
8 Tripura - - - - -
Total 3,980 7,930 17,100 - 29,010
1. Himachal Pradesh - - 3,340 - 3,340
2. Kerala - - 15,000 - 15,000
3. Jharkhand - - - - -
Total - - 18,340 - 18,340
Grand Total (NE+ Others) 3,980 7,930 35,440 - 47,350
The State-wise capacity of construction of godowns from 2016-17 to 2019-20 (up to 31.05.2019) by the respective State Governments is as below:-
(figures in MT)
Sl Name of the State 2016-17 2017-18 2018-19 2019-20
(up to 31.05.2019) Cumulative capacity completed from 01.04.2016 to 31.05.2019
1 Assam - - - - -
2 Mizoram - 2,000 - - 2,000
3 Meghalaya - - - - -
4 Sikkim - - - - -
5 Tripura 15,000 2,500 - - 17,500
6 Arunachal Pradesh 640 - 225 - 865
7 Nagaland - - 1,280 - 1,280
Total 15,640 4,500 1,505 - 21,645
Grand Total=68,955
****
Annexure-IV
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The State-wise details of ongoing projects under Central Sector Scheme “Storage & Godowns” 2017-20 by FCI (as on 31.05.2019) is as below:-
State Capacity
(MT)
Assam 20,000
Arunachal Pradesh 2,790
Manipur 7,500
Meghalaya 2,500
Himachal Pradesh 6,220
Total 39,010
The State-wise details of ongoing projects under Central Sector Scheme “Storage & Godowns” 2017-20 by State Governments (as on 31.05.2019) is as below:-
SL State Capacity (in MT)
1 Assam 16,000
2 Arunachal Pradesh 400
3 Mizoram 4,450
4 Nagaland 2,560
5 Sikkim 3,450
6 Tripura 2,000
Total 28,860
****
Annexure-V
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
Year wise and region wise funds allocated under Central Sector (erstwhile Plan) Scheme “Storage & Godowns” and actual fund released and utilized by FCI.
(in Rs. crore)
Components 2016-17 2017-18 2018-19 2019-20 Funds utilized by FCI from 01.04.2016 to 31.05.2019
RE AFR RE AFR RE AFR BE AFR
(up to 31.05.2019)
North East (NE) head of FCI 50.00 35.75 23.50 23.50 63.00 63.00 45.00 - 151.14
Other than North East (ONE) head of FCI - - - - - - 04.00 - 18.58
Total 50.00 35.75 23.50 23.50 63.00 63.00 49.00 - 169.72
BE=Budget estimates
RE=Revised estimates
AFR=Actual Funds released
Year wise and State wise funds allocated under Central Sector (erstwhile Plan) Scheme “Storage & Godowns” and actual fund released and utilized by State Governments.
(in Rs. Cr.)
Sl Name of the State 2016-17 2017-18 2018-19 2019-20 Funds utilized by State Governments against funds released from 01.04.2016 to 31.05.2019
RE AFR RE AFR RE AFR BE AFR (up to 31.05.2019)
1 Assam 2.00 - 29.32 09.57 23.30 - 21.00 - -
2 Arunachal
Pradesh 10.36 08.04 - - 05.04
3 Mizoram 01.64 - 14.42 - 01.64
4 Nagaland 04.25 04.00 - 05.91
5 Sikkim - 11.71 - - -
6 Tripura - - 04.88 - -
Total 2.00 16.25 29.32 29.32 23.30 23.30 21.00 - 12.59
BE=Budget estimates
RE=Revised estimates
AFR=Actual Funds released
******
Annexure-VI
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The State/UT-wise details of silos created under the road map/action plan during the last 3 years, current year (up to 31.05.2019) are given below:
Year Silo created
(LMT)
2016-17 6.00
2017-18 0.25
2018-19 0.50
2019-20
(up to 31.05.2019) -
Total 6.75
The State/UT-wise details of ongoing projects of construction of silos (as on 31.05.2019) are given below:
SL State Capacity
(in LMT)
1 Assam 0.50
2 Bihar 0.50
3 Punjab 2.00
4 Uttar Pradesh 0.50
5 Haryana 1.50
6 Gujarat 0.50
Total 5.50
****
Annexure-VII
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The State/UT-wise details of silos planned in the country as per the action plan/road map approved by Government of India are as given below:
(figures in LMT)
SL State Capacity planned
1 Andhra Pradesh 3.50
2 Assam 0.50
3 Bihar 9.50
4 Chhattisgarh 1.00
5 Delhi 1.00
6 Gujarat 3.00
7 Haryana 9.50
8 Karnataka 0.25
9 Madhya Pradesh 10.00
10 Maharashtra 1.50
11 Odisha 2.00
12 Punjab 31.00
13 Rajasthan 6.25
14 Telangana 1.50
15 Uttar Pradesh 12.00
16 West Bengal 7.50
Total 100.00
***
Annexure-VIII
ANNEXURE REFERRED TO IN REPLY TO PARTS (a) TO (e) OF THE UNSTARRED QUESTION NO.2715 DUE FOR ANSWERED ON 09.07.2019 IN THE LOK SABHA.
The grant approved by Ministry of Finance, Government of India, for construction of silos in VGF model during the last three years and current year i.e. 2019-20 (up to 31.05.2019) is given below:
SL Year Grant Approved
(in Rs Cr) State
1 2016-17 - -
2 2017-18 - -
3 2018-19 5.31 Punjab
4 2019-20
(up to 31.05.2019) - -
Total 5.31
***