(a) whether the development of Kargil Airport has been undertaken by the Govenment;and
(b) if so, the details thereof and the current status thereof?
(a) whether the development of Kargil Airport has been undertaken by the Govenment;and
(b) if so, the details thereof and the current status thereof?
MINISTER OF THE STATE (INDEPENDENT CHARGE) IN THE MINISTRY OF CIVIL AVIATION (SHRI PRAFUL PATEL)
(a) & (b) No, Sir. However, on the request of State Government, a team of Airports Authority
of India visited Kargil Airport on 30.07.2009 to carry out a pre-feasibility study for taking
up development works. Runway extension by 1500ft over the existing 6000ft and other associated
works are planned in order to enable operation by ATR-72 type of aircraft. This is at an
estimated cost of Rs.46.50 crores (approx.). The State Government has been requested to provide
necessary funds.