Question : KARGIL AIRPORT



(a) whether the development of Kargil Airport has been undertaken by the Govenment;and

(b) if so, the details thereof and the current status thereof?

Answer given by the minister


MINISTER OF THE STATE (INDEPENDENT CHARGE) IN THE MINISTRY OF CIVIL AVIATION (SHRI PRAFUL PATEL)

(a) & (b) No, Sir. However, on the request of State Government, a team of Airports Authority of India visited Kargil Airport on 30.07.2009 to carry out a pre-feasibility study for taking up development works. Runway extension by 1500ft over the existing 6000ft and other associated works are planned in order to enable operation by ATR-72 type of aircraft. This is at an estimated cost of Rs.46.50 crores (approx.). The State Government has been requested to provide necessary funds.