THE MINISTER OF POWER
( SHRI SUSHILKUMAR SHINDE )
(a) to (e) : A Statement is laid on the Table of the House.
STATEMENT
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (e) OF
STARRED QUESTION NO. 94 TO BE ANSWERED IN THE LOK SABHA
ON 17.08.2007 REGARDING COMPLETION OF ON-GOING POWER
PROJECTS.
(a) : The following steps have been taken by the Government to facilitate the
development of power projects:
(i) With the coming into effect of the Electricity Act, 2003 the techno-economic
clearance of Central Electricity Authority (CEA) is no longer required for
thermal generation projects.
(ii) Concurrence of CEA is now required only for setting up of Hydro electric
schemes whose estimated capital expenditure exceeds the notified limits
indicated below:-
Rs.2500 crores, provided that:
# The scheme is included in National Electricity Plan (NEP) as notified by CEA and conforms to the capacity and type as mentioned in the NEP, and
# The site for setting up the hydro generating station has been allocated through the transparent process of bidding in accordance with the guidelines issued by the Central Government.
Rs.500 crore for any other schemes not covered as stated above.
(iii) The Electricity Act mandates that the Central Transmission Utility, State Transmission Utilities and Transmission licencees shall provide non- discriminatory open access to their transmission systems. This has provided flexibility to the generating companies to choose the buyers of electricity generated by them.
(iv) The requirement of obtaining `in principle` approval of the Planning Commission and procedure of examination by Pre Public Investment Board in respect of power projects has been dispensed with in order to reduce the time cycle of sanctioning of public sector projects.
(v) A 50,000 MW hydro initiative has already been launched and the National Electricity Policy lays maximum emphasis on full development of the feasible hydro potential.
(vi) The Tariff Policy, which was notified on 6th January, 2006 provides that all future requirement of power should be procured competitively by distribution licensees except in cases of expansion of existing projects or where there is a State controlled/owned company as an identified developer. For Public Sector projects, tariff of all new generation and transmission projects should be decided on the basis of competitive bidding after a period of five years or when the Regulatory Commission is satisfied that the situation is ripe to introduce such competition.
(vii) Competitive procurement is required to be done through tariff based bidding which provides flexibility to supplies on internal operations while ensuring certainly on availability of power and tariffs for buyers. Further, the Special Purpose Vehicle (SPV) model which is one of the routes for developing power projects through tariff based bidding ensures tying up of various linkages for the projects before these are handed over to the developers.
In addition, the monitoring mechanism has been strengthened. CEA has appointed a nodal officer for each of the on-going projects. Regular quarterly review meetings with CEA, CPSUs and other stakeholders are being held in the Ministry. In the recently concluded Chief Ministers` Conference it has been resolved to set up a National Power Project Management Board for monitoring the progress and to ensure timely commissioning of the capacity addition and associated transmission projects.
(b) : A capacity addition of about 6853 MW was achieved during 2006-07.
Details are given in Annex-I. At present capacity aggregating 50,910 MW is under
construction. 1935 MW capacity has been already commissioned in 2007-08 and
capacity aggregating 14,400 MW could be completed in 2007-08. Details of these
projects are given at AnnexâII.
(c) : No proposal, at present, is pending with Central Electricity Authority for
according the concurrence.
(d) & (e) : Yes, Sir. Delays in supply of critical equipment has been one of the
reasons for slippages in executing the power projects in the recent past. The working of
the Bharat Heavy Electricals Limited (BHEL), which is the major manufacturer of plant
and equipment in the public sector, is being regularly reviewed by the Ministry of Heavy
Industry and Public Enterprises; furthermore, BHEL is augmenting its capacity to 10,000
MW by December, 2007 and further to 15,000 MW by December, 2009.