Question : Delay in Construction Work

(a) whether the Government has received any complaint pertaining to delay in execution of construction work being undertaken by Border Road Organisation in Jammu and Kashmir;

(b) if so, the details thereof;

(c) whether the Government has fixed the responsibility of any officer of Border Road Organisation in this regard; and


(d) if so, the details thereof and the action taken / being taken against the officers responsible in this regard?

Answer given by the minister


A N S W E R
MINISTER OF STATE (DR. SUBHASH BHAMRE)
IN THE MINISTRY OF DEFENCE


(a) to (d): No, Madam. However, certain delays in execution of road projects have occurred mainly due to the following reasons:-

(i) Delay in Forest / Wildlife clearance.
(ii) Hard rock stretches.
(iii) Limited working season
(iv) Difficulties in availability of construction material.
(v) Delay in land acquisition.

Nobody could be blamed for the delay due to the above reasons. However, compensation for the delay from contractors is levied as per the provision of Contract wherever applicable.
******