THE MINISTER OF HEALTH & FAMILY WELFARE (SHRI GHULAM NABI AZAD)
(a) to (c): Civil work for Package I (Medical College) has started at all the six sites
in last week of May, 2010 and is scheduled to be completed in 15 months except in Patna where
the duration is 18 months. As regards Package II (Hospital), work has started at all the sites
in mid-September, 2010 and is scheduled to be completed in 24 months. Construction of residential
complexes has been undertaken as a separate activity and has started in October-November, 2008
except at Jodhpur where the work started in November, 2007. The details of present status; funds
allocated and name of construction companies engaged for setting up of the AIIMS-like institutions
are given at Annexure.
(d) & (e): Construction of residential complex at many of the sites has delayed due to site
specific issues such as encroachments, agitation from local people, and issues related to clearing
of site by State authorities such as tree cutting, removal of high transmission line, etc.
Construction of the medical college complex at Rishikesh is likely to be delayed as the
structural analysis had to be re-done. At Bhubaneswar, there has been resistance from local
people against pre-construction mobilization by the contractor. As such, the work at Rishikesh
and Bhubaneswar sites is slightly behind the schedule.
(b) & (f): In order to expedite the work and to avoid delay, strong incentive and disincentive
clauses have been incorporated in the tender conditions for construction of Medical College and
Hospital Complex in the AIIMS institutions being set up under the Pradhan Mantri Swasthya Suraksha
Yojana (PMSSY). to (c) Civil work for Package I (Medical College) has started at all the six
sites in last week of May, 2010 and is scheduled to be completed in 15 months except in Patna
where the duration is 18 months. As regards Package II (Hospital), work has started at all the
sites in mid-September, 2010 and is scheduled to be completed in 24 months. Construction of
residential complexes has been undertaken as a separate activity and has started in October-
November, 2008 except at Jodhpur where the work started in November, 2007. The details of
present status; funds allocated and name of construction companies engaged for setting up of the
AIIMS-like institutions are given at Annexure.
(d) & (e): Construction of residential complex at many of the sites has delayed due to
site specific issues such as encroachments, agitation from local people, and issues related
to clearing of site by State authorities such as tree cutting, removal of high transmission
line, etc.
Construction of the medical college complex at Rishikesh is likely to be delayed as
the structural analysis had to be re-done. At Bhubaneswar, there has been resistance from
local people against pre-construction mobilization by the contractor. As such, the work at
Rishikesh and Bhubaneswar sites is slightly behind the schedule.
(f): In order to expedite the work and to avoid delay, strong incentive and disincentive
clauses have been incorporated in the tender conditions for construction of Medical College
and Hospital Complex in the AIIMS institutions being set up under the Pradhan Mantri Swasthya
Suraksha Yojana (PMSSY).