Question : N.H. NO. IN KANPUR



(a) whether at National Highway No.2 in Kanpur of Uttar Pradesh ambitious project of Bhaunti to Ahirvan/Chhibuli flyover and making National Highway eight lane and at some places six lane has been completed;

(b) if so, the date of completion of the above work;

(c) if not, the expected date of completion of the work; and

(d) the reasons for the delay so far?

Answer given by the minister

THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K.H. MUNIYAPPA)

(a) to (c) A four lane elevated carriage way and service roads from Bhunti to Ahirvan / Chhibuli in Kanpur is under construction. The work is scheduled to be completed by June, 2006.

(d) Acquisition of land and shifting of utilities are the main reasons for delay in the work.