Question : STATUS OF GOLDEN QUADRILATERAL PROJECT

to the replies given to USQ No. 1218 dated December 8, 2004, SQ No. 34 dated March 2, 2005 & USQ No. 2035 dated December 6, 2005 and state:

(a) the present date of completion of the Golden Quadrilateral Project and the reasons for frequent change of completion dates of projects under it; and

(b) the details of the Projects likely to be completed/not likely to be completed by June, 2006?

Answer given by the minister



THE MINISTER OF STATE IN THE MINISTRY OF SHIPPING, ROAD TRANSPORT AND HIGHWAYS (SHRI K. H. MUNIYAPPA)

(a) and (b) It is expected that about 96% of length of Golden Quadrilateral Project would be completed by June 2006.

The details of projects which are likely to be completed by June 2006 are enclosed as Annex -I. Details of projects which are not likely to be completed in full length by June 2006 are enclosed as Annex-II. Reasons for delay if any, for each contract is also indicated in Annex I & II.