Question : Four-Laning Project

(a) the details and the present status of four-laning project on National Highway-30 from Raipur to Jabalpur;

(b) the target fixed for construction of this highway along with the work completed so far; and

(c) whether the Government proposes to make a bypass on Keshkal Ghati, Bastar on this route and if so, the details thereof?



Answer given by the minister

THE MINISTER OF ROAD TRANSPORT AND HIGHWAYS
(SHRI NITIN JAIRAM GADKARI)

(a) & (b) Only one four-laning project on NH-30 from Raipur to Jabalpur namely “4/6 Laning of Raipur-Simga Section of NH-200 (New NH-30) from Km 0+000 to Km 48+580 (Pkg-I) on EPC Mode” having length of 48.58 km for Rs. 513.00 Crores is under implementation with so far completed length of 41.6 km and targeted for completion by June, 2020.

(c) Yes sir, Keshkal bypass of length 11.38 km is a part of the under implementing project work “Rehabilitation and up-gradation of NH-43 from Km.130.00 to 180.000 (Kanker to Bedma) to two lane with paved shoulders under NHDP-IV on EPC basis” in the State of Chhattisgarh.

*****